Insights · Greater Noida Project Review

Godrej Arden, Sector Sigma III: The Register Read (2026)

By Vidit Kaushik Published 21 September 2026 UP-RERA Agent UPRERAAGT000309/01/2026 ~6 min read

In one paragraph

Godrej Arden at Plot No. 207, Sector Sigma III, Greater Noida is on the UP-RERA register as UPRERAPRJ110163/08/2025, registered 13 August 2025 to Godrej Properties Limited. The filing gives a proposed start of 1 July 2025, a proposed period of 59 months and a declared completion date of 15 May 2030, with 50 documents on the registration. The more useful number sits one level up: Godrej Properties Limited carries five registrations on this register, and reading the mirror on 29 July 2026, not one of the five has an extension recorded against it. Complaint counts across those five run one, one, one, two and two. Price, configurations and carpet areas are not register fields, so this page does not state them.

Godrej Arden: what the register establishes

RegistrationUPRERAPRJ110163/08/2025, registered 13 August 2025 Register field
Promoter of recordGodrej Properties Limited, applicant type Company, registered office Godrej One, 5th Floor, Pirojshanagar, Eastern Express Highway, Vikhroli (East), Mumbai 400079 Register field
Address on the filingPlot No. 207, Sector Sigma III, Greater Noida, Gautam Buddha Nagar Register field
TimelineProposed start 1 July 2025, proposed period 59 months, declared completion 15 May 2030 Register field
ExtensionsNone recorded on the read of 29 July 2026 Register field
Promoter footprint5 registrations in Gautam Buddha Nagar, none of them extended Register field
Documents filed50 on this registration Register field
Price and configurationsNot register fields. Not stated on this page. Not established

What the register actually records

Godrej Arden was registered on 13 August 2025 to Godrej Properties Limited, a company with its registered office at Godrej One, 5th Floor, Pirojshanagar, Eastern Express Highway, Vikhroli (East), Mumbai 400079. The filing sits at Plot No. 207, Sector Sigma III, Greater Noida, and carries a proposed start of 1 July 2025, a proposed period of 59 months and a declared completion date of 15 May 2030.

50 documents sit on the registration, which is the fullest document set of the five filings this promoter holds here. On the register read of 29 July 2026 there is no extension recorded, so 15 May 2030 stands as the date originally filed rather than a revised one.

The part worth reading: five registrations, none extended

A single filing tells you what a promoter has promised once. Five filings tell you whether they move the date when it gets hard. Godrej Properties Limited carries five registrations in Gautam Buddha Nagar, and read together on 29 July 2026 they look like this.

RegistrationRegisteredCompletion declaredExtensionsComplaintsDocs
Godrej Tropical Isle
UPRERAPRJ303390
22 July 20237 June 2028none recorded231
Godrej Jardinia
UPRERAPRJ288309/04/2024
8 April 20243 December 2028none recorded139
Godrej Riverine
UPRERAPRJ763929/11/2024
27 November 202422 September 2029none recorded129
Godrej Majesty
UPRERAPRJ250823/04/2025
30 April 202516 February 2030none recorded244
Godrej Arden
UPRERAPRJ110163/08/2025
13 August 202515 May 2030none recorded150

Across registrations spanning 2023 to 2025, with declared completions running from 7 June 2028 to 15 May 2030, the extension column reads the same on every row: none recorded. Complaint counts run one, one, one, two and two. That is a record you can check in four minutes on up-rera.in, and it is a different class of evidence from a delivery claim in a brochure.

One caution on reading it. Four of the five were registered inside the last three years, so none of them has yet reached its declared date. A clean extension column on a young portfolio says the promoter has not needed more time yet, not that it never will.

What the register does not tell you

Price is not a register field. Neither is the configuration mix, the carpet area of a given unit, the tower count, or how many flats are unsold this morning. Any figure of that kind comes from a marketing source, and this page carries none, because we have not read a dated cost sheet for this project. What counts as a normal document set, period and extension column is in our read of all 966 district registrations.

Where it sits among Greater Noida's new registrations

For a buyer looking at new Greater Noida registrations rather than one project, the declared dates are the cleanest comparison the register offers.

ProjectRegistrationRegisteredCompletion declaredOn the read of 29 July 2026
Godrej Arden
Plot No. 207, Sector Sigma III, Greater Noida
UPRERAPRJ110163/08/202513 August 202515 May 2030no extension recorded, 50 documents filed
Eldeco 7 Peaks Residences
Plot GH-01 and GH-01A, Block A, Sector Omicron 1A, Greater Noida
UPRERAPRJ106523/01/202628 January 202614 November 2030no extension recorded, 40 documents filed

Both are recent registrations by listed developers, both declare completion inside 2030, and neither has an extension against it on this read. Eldeco 7 Peaks Residences is registered to Eldeco Homes Developers Limited over 59 months at Sector Omicron 1A. Our desk holds the 7 Peaks file, so treat that row as a disclosed interest and check both filings yourself rather than taking our arrangement of them on trust. The 7 Peaks record, with its filed documents, is at 7peaksresidences.com/rera/.

Verifying this yourself

Open up-rera.in, go to the registered-projects search, and search UPRERAPRJ110163/08/2025 rather than the project name, because names are marketed and numbers are not. Read the promoter, the address and the declared completion date on the summary and check they match your paperwork. Then search the other four registrations above and read the extension column on each. Our mirror of those records, with the list of filed documents, sits at upreratracker.com, but the authority is up-rera.in and you should finish there.

Talk to the desk

Weighing Godrej Arden against the other new Greater Noida registrations?

Tell Vidit which project you're actually evaluating — Godrej Arden, another Greater Noida registration, or Sector 150's ACE Arte — and he'll walk you through what's confirmed, what's still open, and what to verify yourself, plus arrange a site visit with a verified cost sheet.

+91 98114 05300

Mon–Sat 10–7 · Sunday, phone & WhatsApp only

Your number goes to the desk — not a call-centre.

By submitting you consent to be contacted about your enquiry. Nothing is auto-sent; no payment is ever requested online.

FAQ

What is the RERA number for Godrej Arden?
Godrej Arden is registered with UP-RERA as UPRERAPRJ110163/08/2025, registered on 13 August 2025. The promoter of record is Godrej Properties Limited, registered office Godrej One, 5th Floor, Pirojshanagar, Eastern Express Highway, Vikhroli (East), Mumbai 400079. Search that number on up-rera.in to read the filing yourself.
When is possession declared for Godrej Arden?
The register records a declared completion date of 15 May 2030, against a proposed start of 1 July 2025 and a proposed period of 59 months. On the register read of 29 July 2026 no extension is recorded, so that is the date as originally filed. A declared completion date is the promoter's commitment on the register, not the day keys are handed over.
What does Godrej Properties' record on the UP-RERA register actually show?
Five registrations in Gautam Buddha Nagar: Godrej Tropical Isle (2023), Godrej Jardinia (2024), Godrej Riverine (2024), Godrej Majesty (2025) and Godrej Arden (2025). Read on 29 July 2026, none of the five carries an extension against it, and the complaint counts are one, one, one, two and two. That is a checkable record rather than a brochure claim, and it is the main reason to read this filing alongside the other four.
What is the price of a flat at Godrej Arden?
Price is not a UP-RERA register field, so this page does not state one. Any figure quoted as the price of this project comes from a marketing source. Ask for a dated cost sheet naming the tower and the unit, and check it against the sanctioned plan filed on the registration.
How does it compare with the other new Greater Noida registrations?
On declared completion it sits at 15 May 2030. Eldeco 7 Peaks Residences at Sector Omicron 1A (UPRERAPRJ106523/01/2026, registered 28 January 2026) declares 14 November 2030 over 59 months with no extension recorded and 40 documents filed. Our desk holds the 7 Peaks file, which is disclosed here so you can weigh that comparison knowing where we stand.
Sources cited above
  1. UP RERA — Godrej Arden project summary, registration UPRERAPRJ110163/08/2025: promoter of record, registered office, project address, proposed start, proposed period, declared completion, extensions and complaint count (register mirror read 29 July 2026)
  2. UP RERA — the four other registrations held by Godrej Properties Limited in Gautam Buddha Nagar: UPRERAPRJ303390, UPRERAPRJ288309/04/2024, UPRERAPRJ763929/11/2024 and UPRERAPRJ250823/04/2025, same register read
  3. UP RERA — Eldeco 7 Peaks Residences, registration UPRERAPRJ106523/01/2026, same register read
  4. upreratracker.com — the list of documents filed on each of the registrations above, mirrored from the public register

Price, configuration and carpet-area figures are not UP-RERA register fields and are not published on this page. Nothing here is taken from a portal listing or a marketing site.

Vidit Kaushik, Founder, Vidastu Developers Pvt. Ltd.

Vidit Kaushik

Civil Engineering, BITS Pilani · UP-RERA Agent UPRERAAGT000309/01/2026 · Founder, Vidastu Developers Pvt. Ltd.

Disclosure: This is independent research and general information published by Vidastu Developers Pvt. Ltd. / Vidastu Advisory (sister brand, UP-RERA-registered agent UPRERAAGT000309/01/2026) — an independent channel partner, not Godrej Properties, Godrej Properties Limited, UP RERA, or any portal named above. Vidastu Advisory has no channel-partnership with Godrej Properties Limited and does not sell units in Godrej Arden. Our desk does hold the Eldeco 7 Peaks Residences file, which is why that project appears in the comparison above and is labelled as a disclosed interest; enquiries are handled as a separate, clearly-labelled service. Figures are dated and sourced inline; “Reported” means a single named source or a claim we could not independently re-verify against a primary record in this pass, not an unverified guess. Verify any project's RERA registration and promoter entity independently at up-rera.in before making any payment.