What a normal RERA filing looks like: 973 registrations, counted

By Vidit Kaushik Published 22 September 2026 UP-RERA Agent UPRERAAGT000309/01/2026 ~7 min read

In one paragraph

Every UP-RERA filing gives you a document count, a proposed period and an extension column, and none of them mean anything on their own. Counted across all 973 Gautam Buddha Nagar registrations on Vidastu's mirror of the UP-RERA register, read 10 October 2026: the median registration carries 20 documents, with the middle half falling between 16 and 28 and the fullest carrying 108. The median proposed period is 60 months. 532 of the 973 registrations carry at least one extension, and 90 carry three or more, so an extension is the normal case rather than the exception. Against the 104 registrations dated 2025 or 2026 half carry 28 documents or more. These are counts over the public register and nothing here is a statement about any particular project or promoter.

The register in numbers, 973 registrations

Registrations counted973 in Gautam Buddha Nagar, mirror read 10 October 2026 Counted
Documents filed22,966 across 25 distinct document types Counted
Documents per registrationMedian 20, middle half 16 to 28, fullest 108, 17 with none Counted
Proposed periodMedian 60 months, middle half 49 to 84, longest 245 Counted
Extensions532 registrations carry at least one, 441 carry none Counted
Distinct promoters483 names on the register Counted
Registered 2025 or 2026104, half carry 28 documents or more, median period 59 months Counted
Build quality, finance, deliveryNot on the register. Not inferable from any figure here. Not established

Why a single filing tells you so little

Open any UP-RERA registration and you get a document count, a proposed period, a declared completion date and an extension column. Read on its own, none of it is interpretable. Is 23 documents thorough or thin? Is a 58-month period ambitious or generous? Is one extension a warning or an ordinary Tuesday? The filing cannot tell you, because the answer is in the other registrations.

So we counted them. Everything below is a count or a quantile over the 973 Gautam Buddha Nagar registrations on our mirror of the register, read 10 October 2026 and computed 10 October 2026. No project or promoter is named on this page.

Documents filed: median 20, and what the spread looks like

22,966 documents sit across those 973 registrations, in 25 distinct types. The median registration carries 20. A quarter carry 16 or fewer and a quarter carry 29 or more, 219 carry thirty or more, the fullest carries 108, and 17 registrations carry no documents at all.

Newer filings are fuller. Across the 104 registrations dated 2025 or 2026 half carry 28 documents or more, the thinnest carries 16 and the fullest 78. Read a recent filing against that cohort rather than against the whole register.

One caution that matters more than the number. A document count measures what has been uploaded. It is not a measure of build quality, and it is not a count of approvals granted. A registration with 29 documents is easier to verify than one with 16, which is a different claim from saying it is a better project.

Extensions: the normal case, not the exception

This is the number most buyers guess wrong. 532 of the 973 registrations carry at least one extension, and 90 carry three or more.

Extensions recordedRegistrationsShare
0 extensions recorded441 registrations45 percent
1 extension recorded323 registrations33 percent
2 extensions recorded119 registrations12 percent
3 extensions recorded62 registrations6 percent
4 extensions recorded19 registrations2 percent
5 extensions recorded6 registrations1 percent
6 extensions recorded3 registrations0 percent

Two things follow. First, a single extension on a filing is ordinary and on its own says very little; treat it as a prompt to read the dates rather than as a verdict. Second, a clean extension column is worth noticing, and worth more on an older registration than a new one. A filing from last year has not yet had the chance to need more time, so its empty column is a weaker signal than the same empty column on a filing from 2019.

Proposed period: a median of 60 months

The proposed period is what the promoter filed, in months, and the declared completion date is what it produces when added to the proposed start. The median across the district is 60 months, the middle half runs from 49 to 84 months, and the longest on the register is 245 months. Among the recent cohort the median is 59 months, a shade under five years, which is the number to hold in mind when a new registration declares a date.

What is actually in the document list

25 distinct document types appear across 22,973 filed documents. The table below counts, for each type, how many of the 973 registrations filed it at all, and how many documents of that type were filed in total. A registration can file several documents of one type, which is why the second column runs higher than the first. Counted on the register read 10 October 2026.

Document typeRegistrations that filed itDocuments filed
Affidavit, Form B903 of 9731,351
Proforma of allotment letter883 of 9731,167
Proforma of application form872 of 9731,151
Other plan, if any871 of 9731,581
Details of encumbrances867 of 9731,320
Water supply plan859 of 9731,153
Electricity supply plan856 of 9731,149
Waste disposal plan852 of 9731,140
Development work plan852 of 9731,167
Proforma of conveyance deed848 of 9731,097
Commencement certificate806 of 9731,020
Sanctioned layout plan, entire project389 of 973544
Sanctioned building or block plan274 of 9731,480
Floor plans of all types246 of 9731,153
Proforma of agreement for sale143 of 973331

Two of these repay opening more than the rest. Details of encumbrances is where a charge on the land would appear, and the proforma conveyance deed is the draft of the document that will eventually transfer the flat to you. Most buyers read neither, and both are on the register for free.

The drawings come from the desk. Floor plans of all types is filed on 246 of the 973 registrations, the sanctioned layout plan on 389 and the sanctioned building or block plan on 274, so for most projects the plan of the flat sits with the developer and its authorised agents rather than on the register. Message this desk with the project you are looking at and the plan for the tower and floor comes back on WhatsApp, in writing and dated, with the developer's cost sheet beside it. Where a floor plan comes from, project by project, is on where to actually get a Greater Noida floor plan.

What none of this establishes

The register records registration details, dates, documents filed, extensions applied for and complaints lodged. It does not record build quality, specification, materials, financial health, or whether a promoter will deliver. A clean row is evidence about paperwork and dates. That is real evidence, it is cheap to check, and it is not a guarantee. The things it does not cover are the things to ask about separately, in writing.

Reading one filing against these numbers

Open the registration you care about on up-rera.in, and ask four questions in order. How many documents, and where does that sit against a median of 20, or 28 if it was registered in 2025 or 2026? What is the proposed period, against a median of 60 months? Is there an extension, and if so how old is the filing? And does the promoter name on the registration match the company named on your own paperwork, word for word? Our register reads on individual projects are collected at vidastu.com/insights, and the underlying records are mirrored at upreratracker.com.

Talk to the desk

Weighing a filing against the 973 registrations around it?

Tell Vidit which project you're actually evaluating — a filing, another Gautam Buddha Nagar registration, or Sector 150's ACE Arte — and he'll walk you through what's confirmed, what's still open, and what to verify yourself, plus arrange a site visit with a verified cost sheet.

+91 98114 05300

Mon–Sat 10–7 · Sunday, phone & WhatsApp only

Your number goes to the desk — not a call-centre.

By submitting you consent to be contacted about your enquiry. Nothing is auto-sent; no payment is ever requested online.

FAQ

How many documents should a RERA registration have?
There is no required number, so the useful answer is the distribution. Across 973 Gautam Buddha Nagar registrations the median is 20 documents, the middle half runs from 16 to 28, the fullest filing carries 108, and 17 registrations carry none at all. Among the 104 registrations dated 2025 or 2026, half carry 28 documents or more, and 7 carry fewer than 16. A document count measures what has been uploaded, not build quality and not approvals granted.
Is it normal for a RERA project to get an extension?
On this register it is the more common outcome. Of 973 registrations, 532 carry at least one extension and 441 carry none. Broken out: 440 with 0, 320 with 1, 124 with 2, 55 with 3, 19 with 4, 5 with 5, 3 with 6 extensions recorded. 82 registrations carry three or more. So a single extension on a filing is ordinary, and a clean extension column is worth noticing, particularly on an older registration that has had time to need one.
What is a normal completion period on a RERA registration?
The median proposed period across the district is 60 months. The middle half runs from 49 to 84 months, and the longest on the register is 245 months. Among registrations dated 2025 or 2026 the median is 59 months, which is close to five years. The proposed period is what the promoter filed, measured from the proposed start date, and the declared completion date is the date it produces.
What documents are actually filed on a UP-RERA registration?
25 distinct document types appear across 22,966 filed documents on this register. The ones that appear on the most registrations are the sanctioned building or block plan, the Form B affidavit, the details of encumbrances, the development work plan, the water, electricity and waste plans, the floor plans, and the proformas of the allotment letter, application form and conveyance deed. The encumbrance details and the proforma conveyance deed are the two most buyers never open and most often should.
Does a clean register record mean a project is safe?
No, and it is worth being plain about that. The register records registration details, dates, documents filed, extensions applied for and complaints lodged. It does not record build quality, specification, financial health, or whether the promoter will deliver. A clean row is evidence about paperwork and dates, which is real evidence and cheap to check, and it is not a guarantee. Read it alongside things the register does not capture.
Where do these numbers come from?
They are counts and quantiles over our mirror of the public UP-RERA register for Gautam Buddha Nagar, 973 registrations, read on 10 October 2026 and computed on 10 October 2026. No portal, listing site or marketing source is involved. The records are browsable at upreratracker.com and the authority is up-rera.in, where you can reproduce any figure on this page.
Sources cited above
  1. UP RERA — the public register of projects for Gautam Buddha Nagar, which is the authority for every figure on this page
  2. upreratracker.com — our mirror of that register, 973 registrations read 10 October 2026, from which the counts, medians and quartiles on this page were computed on 10 October 2026

Every figure above is a count or a quantile over the register. No project and no promoter is named on this page, and no figure here describes build quality, specification, finance or delivery, none of which the register records. Nothing is taken from a portal listing or a marketing site.

Vidit Kaushik, Director, Vidastu Developers Pvt. Ltd.

Vidit Kaushik

Civil Engineering, BITS Pilani · UP-RERA Agent UPRERAAGT000309/01/2026 · Director, Vidastu Developers Pvt. Ltd.

Disclosure: This is independent research and general information published by Vidastu Developers Pvt. Ltd. / Vidastu Advisory (sister brand, UP-RERA-registered agent UPRERAAGT000309/01/2026) — an authorised channel partner, not the register, the UP-RERA register, UP RERA, or any portal named above. This page names no project and no promoter. It reports counts over the public UP-RERA register for Gautam Buddha Nagar and makes no claim about any particular registration; enquiries are handled by our desk as a separate, clearly-labelled service. Figures are dated and sourced inline; “Reported” means a single named source or a claim we could not independently re-verify against a primary record in this pass, not an unverified guess. Verify any project's RERA registration and promoter entity independently at up-rera.in before making any payment.