Yamuna Expressway · YEIDA BPMS Portal

YEIDA Building Plan Approval & BPMS Map Sanction for House Construction

A YEIDA building plan can be sanctioned only through the online BPMS portal: since 1 August 2024, YEIDA processes every sanction and completion application online. The allottee logs in with CCP or PMS credentials and picks an architect registered with the Council of Architecture and with YEIDA; the architect uploads the drawings, the Smart-DCR engine checks them against YEIDA’s rules, and the fee is paid once the drawing passes. A sanctioned plan stays valid for 5 years, and the completion certificate is applied for on the same portal once the house is built.

Online only since 1 August 2024 BPMS + Smart-DCR 31 Dec 2026 build window

Sources: YEIDA BPMS portal notice, FAQ and Allottee User Manual 1.0 (bpms.yamunaexpresswayauthority.com, read 2 November 2026); YEIDA Building Regulations 2010, Notification No. 311/77-3-09-8X/09 dated 20 December 2010, Regulations 10, 13, 15, 20 and 24, as transcribed on our regulations page (read 6 October 2026); YEIDA’s 87th board meeting, Times of India, 8 November 2025. Fee amounts are not printed on this page.

No-charge construction window closes 31 Dec 2026

YEIDA’s 87th board meeting (7 November 2025) extended the no-charge construction window to 31 December 2026 for residential allottees with executed lease deeds (Times of India, 8 November 2025). The BPMS sanction is the first step on the critical path, because construction cannot start without it.

See the deadline plan and the phased-completion route →

The BPMS sanction, step by step

These are the steps the YEIDA BPMS portal’s own FAQ and Allottee User Manual describe, with one preparation step before filing and the completion step after building. Each step names its source.

  1. Clear your dues and gather your papers. Clear all YEIDA dues on the PIMS portal first, because a building-plan sanction cannot proceed while dues are pending. Keep your allotment letter, your registered lease deed and the YEIDA-issued site plan ready. The site plan carries your plot’s frontage and depth. Source: this site’s guides to building on a YEIDA plot and to the lease deed
  2. Log in to BPMS. Log in at bpms.yamunaexpresswayauthority.com with your CCP or PMS portal credentials. An OTP is sent to your registered mobile number and email, and you need it at every login. Source: YEIDA BPMS Allottee User Manual 1.0
  3. Select your architect. In the Selection of Architect form, choose an architect from the drop-down list. Only architects registered with the Council of Architecture and with YEIDA appear there, and you may choose any of them. Submit the request. The architect accepts or rejects it, and you are told by SMS and email. Source: YEIDA BPMS Allottee User Manual 1.0
  4. The architect prepares and uploads the drawings. The architect draws the plan to YEIDA’s building regulations, in the CAD format set by the portal’s drawing manual, and uploads it. The Smart-DCR engine runs a pre-check, and every drawing that passes gets a scrutiny report listing each YEIDA rule parameter. The architect can fetch that report online with the Application Reference Number. Source: YEIDA BPMS FAQ
  5. Pay the fee. The fee is paid on the portal, and only once the scrutiny engine has approved the drawing. This page does not print fee amounts, because YEIDA revises them. The portal shows the amount for your file. Source: YEIDA BPMS FAQ
  6. Upload the signed drawing. No hard copy is filed. A scanned copy of the duly signed, scrutiny-approved drawing is uploaded instead. Source: YEIDA BPMS FAQ
  7. YEIDA sanctions the plan or raises an objection. YEIDA’s officers review the file. If the application is objected, you can see the scrutiny outputs, and the portal’s documents tab lists the scrutiny drawing, the scrutiny report and any objection letter. The architect corrects the drawing and resubmits. Source: YEIDA BPMS Allottee User Manual 1.0
  8. Build to the sanctioned plan. Construction follows the sanctioned drawing. The sanction is valid for 5 years. If the house is not complete in that time, the plan has to be revalidated. Source: YEIDA Building Regulations 2010, Regulation 15, on our regulations page
  9. Apply for completion on BPMS. Completion applications also go only through BPMS. The architect certifies that the built house matches the sanctioned drawing, and YEIDA then checks it before issuing the certificate. To qualify, a residential plot needs at least 40 sqm built, or 50 per cent of the maximum permissible ground coverage if that is more, with a functional toilet or bath and a kitchen. An occupancy certificate is mandatory before anyone occupies the building, and the CEO has 90 days to issue it or say why not. Source: YEIDA BPMS portal notice; this site’s guide for new allottees; YEIDA Building Regulations 2010, Regulations 24.1(2)(x) and 20.1.1. More: the YEIDA completion certificate

What is not confirmed. The portal pages we could read for this update do not state a service time for a clean file, so this page no longer quotes one. Our own Vidastu Build page says straightforward residential files typically clear scrutiny in a few weeks. The statutory backstop is the deemed-sanction rule below.

Three guides take the file further.

Who can file: the registered architect

BPMS accepts a plan only from an architect on its own list. Architects register on the portal with their Council of Architecture number. The allottee then picks one from the Selection of Architect list, which shows architects registered with the CoA and with YEIDA. An architect who is not on the portal cannot file your plan, however experienced. That is what this site means by an empanelled architect.

Before you engage anyone, ask for the architect’s CoA registration number, and check that the name appears in the portal’s list when you log in. Vidastu files the plan in-house, with a Council of Architecture registered architect, as part of every build. Ask us which architect would file yours →

Documents to keep ready

The portal sets the upload fields, and we could not confirm a complete official checklist for this update. The table lists what the portal’s own process and this site’s guides call for, so you are not caught short. Check the portal’s list for your file before you apply.

DocumentWhy it is neededSource
Allotment letterIdentifies the plot, its sector and its category. Your plot area comes from this letter, not from any website.How much can I build
Registered lease deedYou build against the lease deed and a sanctioned plan. Registered title is also needed for a loan and the completion certificate.Lease deed guide
YEIDA dues cleared on PIMSA sanction cannot proceed while dues are pending.Building on a YEIDA plot
YEIDA-issued site planCarries the plot’s frontage and depth, which decide what fits inside the setbacks.How much can I build
CCP or PMS login, with your registered mobile and emailNeeded for every BPMS login and its OTP.BPMS Allottee User Manual 1.0
Architect’s drawings, then the signed scrutiny-approved drawingPrepared to the portal’s CAD format. The signed copy is uploaded as a scan; no hard copy is filed.BPMS FAQ
Structural design and the engineer’s stability certificateOur guides list it for basements and for the completion stage. Confirm whether the portal asks for it at sanction for your plot.Construction quality guide
Power of attorney, if someone acts for youAn owner abroad can have a power of attorney holder sign local paperwork.NRI build guide
Identity proof of the allotteeKeep it ready, and check on the portal whether an upload is asked for.Not confirmed on the portal pages we read

Vidastu prepares and coordinates these papers for owners who engage us for a full build. If you only need help with a self-managed filing, WhatsApp us and we will tell you what the portal asks for.

If YEIDA does not decide: the 60-day deemed sanction

Regulation 13(2) of the YEIDA Building Regulations 2010 says that if no decision is given within 60 days of the application, the plan is deemed sanctioned. There is a condition. The applicant must notify the CEO in writing within the next 20 days. Without that notice there is no deemed sanction.

Treat it as a backstop, not a plan. The Regulations date from 2010 and YEIDA can amend them, so confirm with YEIDA how the clock runs on an online file before you rely on it. An earlier version of this page described the rule without the 20-day notice. That was incomplete, and it is corrected here.

Validity and revalidation

A sanctioned plan is valid for 5 years (Regulation 15). If the plan runs out before the house is complete, it has to be revalidated. Revalidating while the plan is still valid costs a fraction of a fresh permit fee. After it expires, the full permit fee applies (Regulations 10(5) and 15). Building on an expired plan without revalidation also attracts a penalty under the Regulations.

This page does not print the fee or the penalty amounts, because YEIDA revises its fees. Check the current figure with YEIDA. The portal pages we read do not describe the revalidation screen, so ask your architect how it is filed for your plot.

Common reasons a file is objected, and how to avoid them

Most objections trace back to a few causes. Each one below is tied to the Regulations or to the portal’s own process.

Ground coverage and FAR at a glance

What fits on your plot is set by Regulation 24.1, Table 1 of the YEIDA Building Regulations 2010, banded by plot size. The summary below comes from this site’s transcription of that table. The detail, worked floor by floor, is on how much you can build on a YEIDA plot, and every plot rule is gathered on YEIDA plot construction rules.

Plot size (sqm)Max ground coverageMax FAR
Up to 30075%1.80
Above 300 to 50065%1.80
Above 500 to 75060%1.50
Above 750 to 1,25055%1.50
Above 1,250 to 1,75050%1.50
Above 1,750 to 2,00045%1.50
Above 2,000 to 3,50045%1.00
Above 3,500 to 4,00040%1.00

Regulation 24.1, Table 1, YEIDA Building Regulations 2010 (Notification No. 311/77-3-09-8X/09, 20 December 2010), as transcribed on our regulations page, read 6 October 2026. Maximum height is 15 m on every band. Setbacks follow the sector’s zonal plan. YEIDA amends its rules, so confirm the figure for your plot before design.

Two allowances shape most designs. A single basement equal to the ground coverage does not count in FAR when it is used for parking, services or storage. Open vehicle ramps in the side setback do not count either. Both are listed on our regulations page.

Filing for a factory? Industrial plots use their own coverage and FAR table (Regulation 24.3), and the approval sits inside a longer compliance ladder: fire NOC, UPPCB, factory licence, functional certificate. See industrial construction on YEIDA plots.

Sanction, build and certificate: one timeline

The sanction, the build and the completion certificate are three stages of one timeline. Construction cannot start until the plan is sanctioned. YEIDA’s no-charge window for residential allottees with executed lease deeds closes on 31 December 2026. If your plot is still empty, the realistic route is phased completion: build and certify the qualifying block first, then finish the rest under the same sanctioned plan. The deadline plan sets it out, the completion certificate guide covers the last step, and building on a YEIDA plot covers every stage from plot to keys.

What Vidastu does on a BPMS file

Vidastu Developers Pvt. Ltd. (CIN U68200UP2023PTC192378) files the building plan in-house, with a Council of Architecture registered architect, as part of every build. It clears scrutiny and builds to the sanctioned design. At the end, the architect who filed the plan certifies that the house matches it, and we file the completion application on BPMS. The firm is a construction company and is not itself UP-RERA registered. The UP-RERA agent registration UPRERAAGT000309/01/2026 belongs to sister brand Vidastu Advisory, for property advice only. Director Ravi Shankar Sharma has built in Greater Noida since 2000, and Director Vidit Kaushik (BITS Pilani) runs builds day to day. There is no rate card: one binding, itemised fixed quote follows a free site walk.

Owners abroad. The BPMS process is online, and a power of attorney holder can sign local paperwork for you. Weekly photo and video updates from your own site arrive on WhatsApp. Full NRI build guide →

YEIDA building plan approval: FAQ

What is the YEIDA BPMS portal, and do I have to use it?
BPMS, the Building Plan Management System, is YEIDA's online portal for building plan sanction. Since 1 August 2024, YEIDA processes every sanction and completion application only online, so there is no counter or paper route left. The allottee logs in at bpms.yamunaexpresswayauthority.com with CCP or PMS credentials and an OTP.
Who can file my building plan on BPMS?
Only an architect registered with the Council of Architecture and with YEIDA. Architects register on the portal with their CoA number, and you pick one from the Selection of Architect list after you log in. The architect then accepts or rejects your request, and you are told by SMS and email.
What is Smart-DCR and what does it check?
Smart-DCR is the automated rules engine inside BPMS. It checks the architect's drawing against YEIDA's rules and amendments, and every drawing that passes its pre-check gets a scrutiny report listing each rule parameter. The fee is paid only after the scrutiny engine approves the drawing, and a scanned copy of the signed, scrutiny-approved drawing is then uploaded.
What documents should I keep ready for a BPMS application?
Your allotment letter, registered lease deed, YEIDA-issued site plan, proof that YEIDA dues are cleared on PIMS, and the CCP or PMS login tied to your registered mobile and email. Your architect prepares the drawings and uploads the signed scrutiny-approved copy. A power of attorney is needed if someone acts for you. The portal sets the final list for your file, so check it before you apply.
What happens if YEIDA does not decide my plan within 60 days?
Under Regulation 13(2) of the YEIDA Building Regulations 2010, no decision within 60 days of the application is a deemed sanction, but only if you notify the CEO in writing within the next 20 days. Treat it as a backstop, and confirm with YEIDA how the clock runs on an online file before you rely on it.
How long is a sanctioned plan valid, and what is revalidation?
A sanctioned plan is valid for 5 years (Regulation 15). If the house is not complete in that time, the plan has to be revalidated. Revalidating within validity costs a fraction of a fresh permit fee, and after expiry the full permit fee applies (Regulations 10(5) and 15). Check the current amount with YEIDA.
What ground coverage and FAR apply to a YEIDA residential plot?
Regulation 24.1, Table 1 sets them by plot size. Plots up to 300 sqm take a maximum ground coverage of 75 per cent and a FAR of 1.80; plots above 300 and up to 500 sqm take 65 per cent and 1.80; plots above 500 and up to 750 sqm take 60 per cent and 1.50. Maximum height is 15 m on every band, and setbacks follow the sector's zonal plan. Confirm the figure for your plot before design.
What happens if I build without a BPMS sanction?
YEIDA will not issue a completion certificate for a house built without a sanctioned plan, and you need that certificate for utilities, a home loan, registry and resale. Construction without a permit also attracts compounding penalties under the Regulations and risks demolition orders. With the no-charge construction window closing on 31 December 2026, get the sanction before any work starts.

Explore more

Also building in: Sector 18 · Sector 20 · Sector 22D · Gaur Yamuna City · Greater Noida · Jewar Airport · Choosing a builder? The 8-point checklist · हिंदी में: YEIDA नक्शा पास (BPMS)

Talk to the desk

Ready to get your YEIDA naksha sanctioned?

Send your allotment details, plot size and the floors you want. We’ll confirm what you can build, line up the architect and put one binding, itemised fixed quote in writing, covering sanction, construction and the completion certificate.

+91 95404 45300

Delivery lead calls back within 24 hours, not a call centre.

Your number goes to the delivery lead, not a call-centre.

Vidastu Build, three packages: Essential · Premium · Luxe, all Vaastu-aligned by design. Priced on call: one binding, itemised fixed quote after a free site walk. See what each package includes →