Insights · The Register, Counted

Who registers projects in Greater Noida? 966 filings, counted

By Vidit Kaushik Published 23 September 2026 UP-RERA Agent UPRERAAGT000309/01/2026 ~7 min read

In one paragraph

Every UP-RERA filing names an applicant type, and it is the field that says what kind of legal entity is on the other side of your agreement. Counted across all 966 Gautam Buddha Nagar registrations on Vidastu's mirror of the UP-RERA register, read 29 July 2026: 861 (89.1 percent) are Companies, 46 are Partnership Firms, 18 are Limited Liability Partnerships, 7 are Individuals, 5 are Societies and 2 are Proprietorship Firms. The remaining 27 are filed by a Competent authority, and those three registrants are the development authorities themselves. The mix is also shifting: LLPs are 1.9 percent of the whole register but 9.3 percent of the 97 filings dated 2025 or 2026.

Applicant type across 966 registrations

Registrations counted966 in Gautam Buddha Nagar, mirror read 29 July 2026 Counted
Distinct applicant types7 Counted
Companies861 filings, 89.1 percent, across 423 distinct promoter names Counted
Filed by a development authority27 filings, from 3 registrants Counted
LLPs, whole register against recent1.9 percent overall, 9.3 percent of the 97 filings dated 2025 or 2026 Counted
Financial standing of any promoterNot on the register. Not inferable from the type. Not established

Why the applicant type is worth ten seconds

Every UP-RERA filing names an applicant type. It is a small field and it answers a large question: what kind of legal entity is on the other side of your agreement. A buyer who knows the project name and not the promoter type knows the marketing and not the counterparty.

Everything below is a count over the 966 Gautam Buddha Nagar registrations on our mirror of the register, read 29 July 2026 and computed 23 September 2026. No developer is named on this page.

The whole register by type

Applicant typeFilingsShareDistinct promotersMedian documents
Company86189.1 percent42320
Partnership Firm464.8 percent2918
Competent authority272.8 percent327
Limited Liability Partnership (LLP)181.9 percent1132
Individual70.7 percent715
Societies50.5 percent414
Proprietorship Firm20.2 percent230

Companies dominate at 89.1 percent, spread across 423 distinct promoter names. The long tail is genuinely long and genuinely small: 7 filings by Individuals, 5 by Societies and 2 by Proprietorship Firms, which together are under two percent of the register.

The 27 filings nobody expects

The highlighted row is the one worth knowing about if you are buying a plot rather than a flat. 27 registrations are filed by a Competent authority, and there are only 3 such registrants on this register: the Greater Noida Industrial Development Authority, the New Okhla Industrial Development Authority and the Yamuna Expressway Industrial Development Authority.

A plot scheme is a project under the Act, so the authority registers it like any promoter. If your allotment came from a scheme rather than a builder, the authority is your promoter of record, its registration number is the one to search, and its filing carries the documents. That is not obvious from anything on an allotment letter, and it is the single most useful thing on this page for a plot allottee.

The mix is shifting toward LLPs

Applicant typeFilings dated 2025 or 2026Share of the cohort
Company8385.6 percent
Limited Liability Partnership (LLP)99.3 percent
Partnership Firm22.1 percent
Competent authority22.1 percent
Proprietorship Firm11.0 percent

LLPs are 1.9 percent of the whole register and 9.3 percent of the 97 filings dated 2025 or 2026. Companies still dominate the recent cohort at 83 of 97. That is a change in the mix and nothing more; the register records no reason for it and neither do we.

The comparison on this page that does not work

The table above tempts an obvious reading, so here is why it fails. Of the 861 Company filings, 490 carry at least one extension. Of the 18 LLP filings, only 6 do. Read as a ranking, that says LLPs hold their dates better.

They do not, or at least this cannot show it. Companies carry almost the entire 2017 to 2019 cohort, which has had eight years in which to need more time. Half the LLP filings are from 2025 or 2026 and have had months. The gap is age, not entity type. Any comparison of extension rates has to hold the registration year constant, which is what our read of completion dates across 957 filings does. We are publishing the raw numbers with the caveat rather than quietly leaving them out, because they are the first thing anyone would compute from this data and the caveat is the useful half.

What the applicant type does not establish

Not financial standing, not delivery capability, not build quality, not whether the entity will still exist in five years. The register records the type, the registered office and the project fields. Treat the type as a fact to verify from: search the registration, read the promoter name and type, and compare them word for word with the entity named on your own allotment letter and agreement. Where the same brand appears under several registered promoters, which is common here, that check is the whole ballgame. What a normal filing looks like on every other field is in our read of all 966 registrations.

Talk to the desk

Weighing a promoter against the 966 registrations around it?

Tell Vidit which project you're actually evaluating — a promoter, another Gautam Buddha Nagar registration, or Sector 150's ACE Arte — and he'll walk you through what's confirmed, what's still open, and what to verify yourself, plus arrange a site visit with a verified cost sheet.

+91 98114 05300

Mon–Sat 10–7 · Sunday, phone & WhatsApp only

Your number goes to the desk — not a call-centre.

By submitting you consent to be contacted about your enquiry. Nothing is auto-sent; no payment is ever requested online.

FAQ

What kinds of promoters are on the UP-RERA register?
Seven applicant types across 966 Gautam Buddha Nagar registrations, read 29 July 2026: Company 861, Partnership Firm 46, Competent authority 27, Limited Liability Partnership (LLP) 18, Individual 7, Societies 5, Proprietorship Firm 2. Companies dominate at 89.1 percent, spread across 423 distinct promoter names.
Why would a development authority register a project on RERA?
Because a plot scheme is a project under the Act. 27 of the registrations here are filed by a Competent authority, and the three registrants are the Greater Noida Industrial Development Authority, the New Okhla Industrial Development Authority and the Yamuna Expressway Industrial Development Authority. If you are buying a plot in an authority scheme rather than a flat from a developer, the authority is the promoter of record and its filing is the one to read.
Does it matter whether the promoter is a company, an LLP or a partnership firm?
It matters that you know which, because the liability structures differ and the entity named on your agreement is the one that owes you the home. What the register does not give you is any measure of financial standing: it records the type, the registered office and the project fields, and nothing more. So treat the applicant type as a fact to verify from rather than a verdict, and check the name on the registration against the name on your allotment letter, word for word.
Are LLPs becoming more common?
On this register, yes. LLPs are 18 of 966 filings overall, about 1.9 percent, but 9 of the 97 registrations dated 2025 or 2026, about 9.3 percent. Companies still dominate the recent cohort at 83 of 97. That is a shift in the mix, not a statement about any of them.
Do partnership firms or LLPs get fewer extensions than companies?
The raw numbers say so and the comparison does not survive contact with the dates, which is why this page publishes both. Of 861 Company filings, 490 carry at least one extension; of 18 LLP filings, 6 do. But Companies carry almost the whole 2017 to 2019 cohort, which has had eight years in which to revise a date, while half the LLP filings are from 2025 or 2026 and have had months. The gap is age, not entity type. Read extension rates against the age of the filing instead.
Where do these numbers come from?
They are counts over our mirror of the public UP-RERA register for Gautam Buddha Nagar, 966 registrations, read 29 July 2026 and computed 23 September 2026. No portal, listing site or marketing source is involved, and no developer is named on this page. The records are browsable at upreratracker.com and the authority is up-rera.in, where any figure here can be reproduced.
Sources cited above
  1. UP RERA — the public register of projects for Gautam Buddha Nagar, the applicant-type field on every registration, which is the authority for each count on this page
  2. upreratracker.com — our mirror of that register, 966 registrations read 29 July 2026, from which the type counts, promoter counts, median document counts and cohort shares were computed on 23 September 2026

Every figure above is a count over the register. No developer is named on this page. Applicant type records the kind of registered entity and nothing about financial standing, delivery capability or build quality, none of which the register captures. Nothing is taken from a portal listing or a marketing site.

Vidit Kaushik, Founder, Vidastu Developers Pvt. Ltd.

Vidit Kaushik

Civil Engineering, BITS Pilani · UP-RERA Agent UPRERAAGT000309/01/2026 · Founder, Vidastu Developers Pvt. Ltd.

Disclosure: This is independent research and general information published by Vidastu Developers Pvt. Ltd. / Vidastu Advisory (sister brand, UP-RERA-registered agent UPRERAAGT000309/01/2026) — an independent channel partner, not the register, the UP-RERA register, UP RERA, or any portal named above. This page names no developer. It reports counts over the applicant-type field on the public UP-RERA register for Gautam Buddha Nagar and makes no claim about the standing or capability of any registered entity; enquiries are handled by our desk as a separate, clearly-labelled service. Figures are dated and sourced inline; “Reported” means a single named source or a claim we could not independently re-verify against a primary record in this pass, not an unverified guess. Verify any project's RERA registration and promoter entity independently at up-rera.in before making any payment.