Cyber Hub 2
Gautam Buddha Nagar, Uttar Pradesh: the record gives no street address
On the registerCyber Hub 2 is registered with UP-RERA as UPRERAPRJ436071/04/2024, registered on 5 April 2024, by Galactic City Pvt Ltd. The completion date on the register is 31 December 2027. This page is the register file as read on 10 October 2026. This desk has not investigated the project, so it gives no advice on it here; ask if you want it investigated.
- Price
- the register carries no price; the desk asks the developer for the dated sheet and sends it in writing
- Registered on
- 5 April 2024registration is registration, not approval or endorsement
- Registration type
- Newregistered before it was sold
- Promoter of record
- GALACTIC CITY PRIVATE LIMITEDas filed; every registration under this name
- Project type
- Commercial
- Declared construction period
- 14 monthsfrom 1 October 2023
- Completion date declared at registration
- 26 November 2024the date declared to UP-RERA, not a commitment to hand over a home on that date
- Completion date on the register now
- 31 December 2027see the extension entries below
- Documents on the register
- 36
Read from the UP-RERA register on 10 October 2026. Every line here can be checked on up-rera.in against the registration number.
Ask the desk
This page holds the register file and nothing else. Ask for anything that is not on it, or ask the desk to investigate this project; you will get an answer in writing or be told we do not have it.
Thanks, we have it.
Opening WhatsApp so we can talk now.
What this record tells a buyer
- The registration type is New: the promoter registered Cyber Hub 2 with UP-RERA before selling it, on 5 April 2024.
- The promoter declared a construction period of 14 months from 1 October 2023. Across 46 commercial registrations in Gautam Buddha Nagar registered 2023 onward that declare one, the median declared period is 59 months.
- The completion date declared at registration was 26 November 2024. The register now shows 31 December 2027, with 1 extension entry listed below.
- 36 documents across 16 document types are on the register for this registration. They include the commencement certificate, the encumbrance declaration, an engineer's certificate, an architect's certificate and a chartered accountant's certificate.
- Galactic City Pvt Ltd has 4 registrations on the UP-RERA register for Gautam Buddha Nagar, made between 2019 and 2024.
- The filed address does not name a sector, so this page places the project only where the record itself does.
The full register file
1 extension entry with the register's own reasons, all 36 documents on record with download links: the complete file for Cyber Hub 2 is kept on UP-RERA Tracker by Vidastu.
Before you book Cyber Hub 2
- Get the price in writing, dated, with its basis. Super, carpet or saleable area, and what the figure leaves out. A number on a phone call is not a price.
- Match the company on your agreement to the promoter of record, GALACTIC CITY PRIVATE LIMITED. Group companies often register under different names.
- Check the registration yourself on up-rera.in against UPRERAPRJ436071/04/2024, including the completion date on record and the extension entries (how to read the file).
- Ask for the sanctioned building plan for your tower and compare it with the brochure.
- Pay only into the project's RERA account named in the agreement, never to a person or an agent.
- Read the draft allotment letter and agreement for sale before the first payment, not after.
- Run the EMI before the token. Our EMI calculator takes the written price, your down payment, the rate your bank quotes and the tenure; it prints nothing it is not given.
What this page does not have
- Price. No rate, basis or date is on file, so none is printed. Ask the desk for whatever is current, in writing.
- Configurations and sizes. The register does not carry unit types or sizes, and this page does not repeat a brochure.
- Amenities and payment plans. None on file.
- Distances. None on file. A distance goes on a page only from a named source with a date.
- Advice. This desk advises only on projects it has investigated. This one has not been, yet.
More from Galactic City Pvt Ltd on the register
Guides for this area
Common questions
Is Cyber Hub 2 registered with UP-RERA?
Yes. Cyber Hub 2 is on the UP-RERA register as UPRERAPRJ436071/04/2024, registered on 5 April 2024. Registration is registration; it is not approval or endorsement of the project.
Who is the promoter of Cyber Hub 2?
The promoter of record is GALACTIC CITY PRIVATE LIMITED, as filed on the register. Check that this is the company named in your agreement before you pay.
What completion date does the register show for Cyber Hub 2?
The register shows 31 December 2027. The date declared at registration was 26 November 2024; the change is recorded as extension entries on the register. A completion date on the register is not a commitment to hand over a home on that date.
Where is Cyber Hub 2?
The register gives no street address for this registration beyond the district, Gautam Buddha Nagar, Uttar Pradesh.
What is the price of Cyber Hub 2?
This page prints no price. The register carries none, and no dated rate or cost sheet from the promoter is on file with this desk. Ask the desk and you will get whatever is current in writing, or be told it is not available.
Has the completion date of Cyber Hub 2 been extended?
The register lists 1 extension entry for this registration. Each entry, with the register's own reason text, is in the full file on UP-RERA Tracker by Vidastu, linked from this page.
Read from the UP-RERA register on 10 October 2026. Directory: every registration this desk has read.