Insights · The Register, Counted

How a RERA extension actually works: 852 of them, counted

By Vidit Kaushik Published 23 September 2026 UP-RERA Agent UPRERAAGT000309/01/2026 ~8 min read

In one paragraph

An extension on a UP-RERA filing is a revised completion date entered on the register, and it is the column buyers read as a black mark without knowing what a normal one looks like. Counted across all 852 extension records on Vidastu's mirror of the UP-RERA register for Gautam Buddha Nagar, read 29 July 2026: they sit on 526 of 966 registrations, the median length is 6 months, and 518 of the 844 records with two readable dates are six months or less. The tail is real but small: 78 run beyond two years. And 455 records state a reason, every one of them the same one, word for word: the six-month force majeure allowance for the covid-19 pandemic.

Extensions across 966 registrations

Extension records counted852, mirror read 29 July 2026 Counted
Registrations carrying at least one526 of 966, 54.5 percent Counted
Median length6 months, quartiles 6 and 12 Counted
Longest single span120 months Counted
Records stating any reason455 of 852; the other 397 give a date and nothing else Counted
Of those, citing covid force majeureall 455, in identical wording Counted
Why any individual date movedNot on the register for 397 of 852 records. Not established

The column everyone misreads

Open any UP-RERA filing and there is an extension column. Most buyers read it as a black mark, and almost nobody knows what a normal entry in it looks like, because nothing published anywhere reads the whole set at once. So here it is read at once: every 852 extension records on the Gautam Buddha Nagar register, sitting on 526 of 966 registrations, 54.5 percent of them.

An extension is a revised completion date entered on the public register, which the Act provides for. The figures below are counts over our mirror of that register, read 29 July 2026 and computed 23 September 2026. No developer is named on this page and nothing here ranks anyone.

A normal extension is six months

LengthRecordsShare
6 months or less51861.4 percent
7 to 12 months18622.0 percent
13 to 24 months627.3 percent
more than 24 months789.2 percent

Across the 844 records whose two dates both parse, the median is 6 months and so is the twenty-fifth percentile, which is another way of saying that six months is not the short end of the distribution. It is the distribution. The seventy-fifth percentile is 12 months.

The tail is real and it is small. 78 records, 9.2 percent, run beyond two years, and the longest single span on this register is 120 months. If you are looking at a filing whose extension runs years rather than months, you are looking at something the register treats as unusual, and that is worth a question. If it runs six months, you are looking at the most common entry on the register.

455 records state a reason. It is the same reason.

455 of the 852 records carry any stated reason at all. The remaining 397 give a revised date and nothing else, which is the first thing to know: on nearly half the extensions on this register, the public filing does not say why.

Of the 455 that do, every single one carries the same parenthetical, identical word for word with only the date in front of it differing:

Six months extension in view of force majeure caused by covid-19 pandemic

It sits on 452 distinct registrations, at most once on almost every one of them, and the recorded span is exactly six months on 452 of the 455. That is the shape of a standard allowance applied across many filings rather than 455 separately argued applications. Treat it as a regulatory allowance the sector received, not as a finding about the project in front of you.

A covid extension does not date a project to 2020

This is the part that misleads, and it misleads in a specific direction. The six months attaches to whatever completion date the filing already carried, so the revised date lands wherever that date already was. On this register the covid-worded records put the new date anywhere from 2020 to 2029.

Year the revised date falls inCovid-worded records
202053
2021150
202283
202386
202439
202530
20266
20275
20281
20292

252 of the 455 covid-worded records, the highlighted rows, put the revised completion date in 2022 or later. Seeing that wording on a filing tells you the allowance was applied to it. It does not tell you the project was behind in 2020, it does not date the project, and reading it either way will lead you to the wrong question at the site visit.

The six months is often not the end of it

Extensions on one registrationRegistrationsShare
1 extension32060.8 percent
2 extensions12423.6 percent
3 extensions5510.5 percent
4 extensions193.6 percent
5 extensions51.0 percent
6 extensions30.6 percent

320 of the 526 registrations with an extension carry exactly one. The other 206 carry two or more, up to 6. And here is the thing that changes how you read them: on 198 of those 206, every extension begins on the day the last one ended. No gap.

A chain of 3 six-month grants is not three separate six-month events. It is eighteen continuous months, entered in three rows. On a registration with more than one extension, the number to read is the date at the end of the chain, against the completion date originally proposed. That single comparison is worth more than the extension count, and both numbers are on the public filing.

What an extension does not establish

Not build quality, not financial standing, not bad faith, and not, by itself, that a project is late today. Older registrations have had more years in which to need a revised date, so a raw count of extensions tracks the age of the filing at least as much as it tracks anything about the promoter. That is why this page counts extensions and ranks nobody, and why a league table of promoters by extension count would be a worse document than this one.

What the column is genuinely good for is a short list of questions you can answer from the public filing before you pay anyone anything: how many extensions, how long the chain runs in total, what date sits at the end of it, and how far that date is from the completion period originally proposed. Our read of completion dates across 957 filings covers that last comparison across the register, what a normal filing looks like covers every other field, and who registers projects here covers the entity on the other side of the agreement.

Talk to the desk

Weighing a registration that carries extensions against the rest of the register?

Tell Vidit which project you're actually evaluating — a registration that carries extensions, another Gautam Buddha Nagar registration, or Sector 150's ACE Arte — and he'll walk you through what's confirmed, what's still open, and what to verify yourself, plus arrange a site visit with a verified cost sheet.

+91 95404 45300

Mon–Sat 10–7 · Sunday, phone & WhatsApp only

Your number goes to the desk — not a call-centre.

By submitting you consent to be contacted about your enquiry. Nothing is auto-sent; no payment is ever requested online.

FAQ

What does an extension on a RERA registration actually mean?
That the promoter entered a revised completion date on the register, which the Act provides for. It is a change to a date, recorded in public, and it is the ordinary case rather than the exception here: 526 of 966 Gautam Buddha Nagar registrations carry at least one, 852 records in total, read 29 July 2026. What it does not tell you is why, because on 397 of those 852 records the register gives a date and no reason at all.
How long is a normal extension?
Six months. Across the 844 records whose two dates both parse, the median length is 6 months, the twenty-fifth percentile is 6 and the seventy-fifth is 12. Put in bands: 518 records are six months or less, 186 are seven to twelve months, 62 are thirteen to twenty-four, and 78 run beyond two years. The longest single span on this register is 120 months.
Why do so many extensions mention covid?
Because a six-month force majeure allowance for the pandemic was available, and it is the only stated reason anywhere on this register. Of the 852 records, 455 carry a reason at all and all 455 of those carry the same parenthetical, identical word for word with only the date differing: “Six months extension in view of force majeure caused by covid-19 pandemic”. It sits on 452 distinct registrations, at most once on almost all of them, and the recorded span is exactly six months on 452 of the 455. That is the shape of a standard allowance applied to many filings, not of 455 separately argued cases, and it says nothing about any one project.
Does a covid extension mean the project was delayed in 2020?
No, and this is the most misread thing on the register. The six months attaches to whatever completion date the filing already carried, so the new date lands wherever that date was. On this register those new dates run from 2020 to 2029: 252 of the 455 covid-worded records put the revised date in 2022 or later. Seeing that wording on a filing tells you the allowance was applied. It does not date the project, and it does not tell you the project was behind.
If a project got a six-month extension, is six months the whole story?
Often, and on a large minority it is not. 320 of the 526 registrations with an extension carry exactly one. The other 206 carry two or more, up to 6. And on 198 of those 206, every extension begins on the day the last one ended, with no gap. So on a registration with a run of them, read the last date in the chain rather than the length of any single grant, and read it against the original proposed completion date.
Is a project with extensions a worse project?
The register does not support that reading and neither do we. An extension is a regulatory instrument: it records that a date moved and, on most records here, not why. Older filings have had more years in which to need one, so a count of extensions tracks the age of a registration at least as much as anything about the promoter. What it is good for is a specific question to ask: how many, how long in total, and what is the date at the end of the chain. That question is answerable from the public filing before you pay anyone anything.
Where do these numbers come from?
They are counts over our mirror of the public UP-RERA register for Gautam Buddha Nagar, 852 extension records across 966 registrations, read 29 July 2026 and computed 23 September 2026. No portal, listing site or marketing source is involved, and no developer is named on this page. The records are browsable at upreratracker.com and the authority is up-rera.in, where any figure here can be reproduced.
Sources cited above
  1. UP RERA — the public register of projects for Gautam Buddha Nagar, the extension records filed against each registration, which is the authority for every count on this page
  2. upreratracker.com — our mirror of that register, 852 extension records across 966 registrations read 29 July 2026, from which the lengths, bands, per-registration counts and stated reasons were computed on 23 September 2026

Every figure above is a count over the register. No developer is named on this page and no promoter is ranked. An extension records that a completion date moved; on 397 of 852 records the register states no reason, and it captures nothing about build quality, financial standing or good faith. Nothing is taken from a portal listing or a marketing site.

Vidit Kaushik, Founder, Vidastu Developers Pvt. Ltd.

Vidit Kaushik

Civil Engineering, BITS Pilani · UP-RERA Agent UPRERAAGT000309/01/2026 · Founder, Vidastu Developers Pvt. Ltd.

Disclosure: This is independent research and general information published by Vidastu Developers Pvt. Ltd. / Vidastu Advisory (sister brand, UP-RERA-registered agent UPRERAAGT000309/01/2026) — an independent channel partner, not the register, the UP-RERA register, UP RERA, or any portal named above. This page names no developer and ranks no promoter. It reports counts over the extension records on the public UP-RERA register for Gautam Buddha Nagar and makes no claim about the conduct or capability of any registered entity; enquiries are handled by our desk as a separate, clearly-labelled service. Figures are dated and sourced inline; “Reported” means a single named source or a claim we could not independently re-verify against a primary record in this pass, not an unverified guess. Verify any project's RERA registration and promoter entity independently at up-rera.in before making any payment.