Projects / Greater Noida / Sector 1
Future estate (Phase-fe-1)
Plot No. GH16E, Sector-01, Greater Noida West, Uttar Pradesh, Gautam Buddha Nagar, Pin 201308, Gautam Buddha Nagar
On the registerFuture estate (Phase-fe-1) is registered with UP-RERA as UPRERAPRJ7361, registered on 14 August 2017, by Futureworld Greenhomes Pvt Ltd. The completion date on the register is 31 July 2026. This page is the register file as read on 10 October 2026. This desk has not investigated the project, so it gives no advice on it here; ask if you want it investigated.
- Price
- the register carries no price; the desk asks the developer for the dated sheet and sends it in writing
- Registered on
- 14 August 2017registration is registration, not approval or endorsement
- Registration type
- Ongoingunder way when it was registered
- Promoter of record
- FUTUREWORLD GREENHOMES PVT. LTD.as filed; every registration under this name
- Project type
- Residential
- Declared construction period
- 42 months
- Completion date declared at registration
- 31 December 2018the date declared to UP-RERA, not a commitment to hand over a home on that date
- Completion date on the register now
- 31 July 2026see the extension entries below
- Documents on the register
- 23
- Sector, as filed
- Sector 1
Read from the UP-RERA register on 10 October 2026. Every line here can be checked on up-rera.in against the registration number.
Ask the desk
This page holds the register file and nothing else. Ask for anything that is not on it, or ask the desk to investigate this project; you will get an answer in writing or be told we do not have it.
Thanks, we have it.
Opening WhatsApp so we can talk now.
What this record tells a buyer
- The registration type is Ongoing: the project was already under way when it was registered, which is how projects begun before RERA registration became mandatory appear on the register.
- The promoter declared a construction period of 42 months. Across 39 residential registrations in Greater Noida registered before 2023 that declare one, the median declared period is 66 months.
- The completion date declared at registration was 31 December 2018. The register now shows 31 July 2026, with 6 extension entries listed below.
- 23 documents across 18 document types are on the register for this registration. They include the sanctioned building plan, the sanctioned layout plan, the commencement certificate, the encumbrance declaration, an engineer's certificate, an architect's certificate and a chartered accountant's certificate.
- Futureworld Greenhomes Pvt Ltd has 7 registrations on the UP-RERA register for Gautam Buddha Nagar, made in 2017.
- The filed address names Sector 1.
The full register file
6 extension entries with the register's own reasons, all 23 documents on record with download links: the complete file for Future estate (Phase-fe-1) is kept on UP-RERA Tracker by Vidastu.
Before you book Future estate (Phase-fe-1)
- Get the price in writing, dated, with its basis. Super, carpet or saleable area, and what the figure leaves out. A number on a phone call is not a price.
- Match the company on your agreement to the promoter of record, FUTUREWORLD GREENHOMES PVT. LTD.. Group companies often register under different names.
- Check the registration yourself on up-rera.in against UPRERAPRJ7361, including the completion date on record and the extension entries (how to read the file).
- Ask for the sanctioned building plan for your tower and compare it with the brochure.
- Pay only into the project's RERA account named in the agreement, never to a person or an agent.
- Read the draft allotment letter and agreement for sale before the first payment, not after.
- Run the EMI before the token. Our EMI calculator takes the written price, your down payment, the rate your bank quotes and the tenure; it prints nothing it is not given.
What this page does not have
- Price. No rate, basis or date is on file, so none is printed. Ask the desk for whatever is current, in writing.
- Configurations and sizes. The register does not carry unit types or sizes, and this page does not repeat a brochure.
- Amenities and payment plans. None on file.
- Distances. None on file. A distance goes on a page only from a named source with a date.
- Advice. This desk advises only on projects it has investigated. This one has not been, yet.
More from Futureworld Greenhomes Pvt Ltd on the register
Other registrations in Sector 1
- On the registerFuture Estate(Phase-Fe-2)
- On the registerFuture Estate (Phase-fe-3)
- On the registerFuture Estate (Phase -fe-4)
- On the registerRhythm County(Phase Rc-1)
- On the registerRhythm County (Phase Rc-2)
- On the registerRhythm County (Phase Rc-3)
Guides for this area
Common questions
Is Future estate (Phase-fe-1) registered with UP-RERA?
Yes. Future estate (Phase-fe-1) is on the UP-RERA register as UPRERAPRJ7361, registered on 14 August 2017. Registration is registration; it is not approval or endorsement of the project.
Who is the promoter of Future estate (Phase-fe-1)?
The promoter of record is FUTUREWORLD GREENHOMES PVT. LTD., as filed on the register. Check that this is the company named in your agreement before you pay.
What completion date does the register show for Future estate (Phase-fe-1)?
The register shows 31 July 2026. The date declared at registration was 31 December 2018; the change is recorded as extension entries on the register. A completion date on the register is not a commitment to hand over a home on that date.
Where is Future estate (Phase-fe-1)?
The address as filed is Plot No. GH16E, Sector-01, Greater Noida West, Uttar Pradesh, Gautam Buddha Nagar, Pin 201308, Gautam Buddha Nagar, Uttar Pradesh.
What is the price of Future estate (Phase-fe-1)?
This page prints no price. The register carries none, and no dated rate or cost sheet from the promoter is on file with this desk. Ask the desk and you will get whatever is current in writing, or be told it is not available.
Has the completion date of Future estate (Phase-fe-1) been extended?
The register lists 6 extension entries for this registration. Each entry, with the register's own reason text, is in the full file on UP-RERA Tracker by Vidastu, linked from this page.
Read from the UP-RERA register on 10 October 2026. Directory: every registration this desk has read.