Grandthum Phase IV
Gautam Buddha Nagar, Uttar Pradesh: the record gives no street address
On the registerGrandthum Phase IV is registered with UP-RERA as UPRERAPRJ103135, registered on 2 September 2019, by A L Softweb Pvt Ltd. The completion date on the register is 26 September 2026. This page is the register file as read on 10 October 2026. This desk has not investigated the project, so it gives no advice on it here; ask if you want it investigated.
- Price
- the register carries no price; the desk asks the developer for the dated sheet and sends it in writing
- Registered on
- 2 September 2019registration is registration, not approval or endorsement
- Registration type
- Newregistered before it was sold
- Promoter of record
- A L SOFTWEB PRIVATE LIMITEDas filed; every registration under this name
- Project type
- Commercial
- Declared construction period
- 47 monthsfrom 1 August 2019
- Completion date declared at registration
- 30 June 2023the date declared to UP-RERA, not a commitment to hand over a home on that date
- Completion date on the register now
- 26 September 2026see the extension entries below
- Documents on the register
- 17
Read from the UP-RERA register on 10 October 2026. Every line here can be checked on up-rera.in against the registration number.
Ask the desk
This page holds the register file and nothing else. Ask for anything that is not on it, or ask the desk to investigate this project; you will get an answer in writing or be told we do not have it.
Thanks, we have it.
Opening WhatsApp so we can talk now.
What this record tells a buyer
- The registration type is New: the promoter registered Grandthum Phase IV with UP-RERA before selling it, on 2 September 2019.
- The promoter declared a construction period of 47 months from 1 August 2019. Across 134 commercial registrations in Gautam Buddha Nagar registered before 2023 that declare one, the median declared period is 49 months.
- The completion date declared at registration was 30 June 2023. The register now shows 26 September 2026, with 4 extension entries listed below.
- 17 documents across 15 document types are on the register for this registration. They include the commencement certificate, the encumbrance declaration, an engineer's certificate, an architect's certificate and a chartered accountant's certificate.
- A L Softweb Pvt Ltd has 5 registrations on the UP-RERA register for Gautam Buddha Nagar, made between 2019 and 2026.
- The filed address does not name a sector, so this page places the project only where the record itself does.
The full register file
4 extension entries with the register's own reasons, all 17 documents on record with download links: the complete file for Grandthum Phase IV is kept on UP-RERA Tracker by Vidastu.
Before you book Grandthum Phase IV
- Get the price in writing, dated, with its basis. Super, carpet or saleable area, and what the figure leaves out. A number on a phone call is not a price.
- Match the company on your agreement to the promoter of record, A L SOFTWEB PRIVATE LIMITED. Group companies often register under different names.
- Check the registration yourself on up-rera.in against UPRERAPRJ103135, including the completion date on record and the extension entries (how to read the file).
- Ask for the sanctioned building plan for your tower and compare it with the brochure.
- Pay only into the project's RERA account named in the agreement, never to a person or an agent.
- Read the draft allotment letter and agreement for sale before the first payment, not after.
- Run the EMI before the token. Our EMI calculator takes the written price, your down payment, the rate your bank quotes and the tenure; it prints nothing it is not given.
What this page does not have
- Price. No rate, basis or date is on file, so none is printed. Ask the desk for whatever is current, in writing.
- Configurations and sizes. The register does not carry unit types or sizes, and this page does not repeat a brochure.
- Amenities and payment plans. None on file.
- Distances. None on file. A distance goes on a page only from a named source with a date.
- Advice. This desk advises only on projects it has investigated. This one has not been, yet.
More from A L Softweb Pvt Ltd on the register
Guides for this area
Common questions
Is Grandthum Phase IV registered with UP-RERA?
Yes. Grandthum Phase IV is on the UP-RERA register as UPRERAPRJ103135, registered on 2 September 2019. Registration is registration; it is not approval or endorsement of the project.
Who is the promoter of Grandthum Phase IV?
The promoter of record is A L SOFTWEB PRIVATE LIMITED, as filed on the register. Check that this is the company named in your agreement before you pay.
What completion date does the register show for Grandthum Phase IV?
The register shows 26 September 2026. The date declared at registration was 30 June 2023; the change is recorded as extension entries on the register. A completion date on the register is not a commitment to hand over a home on that date.
Where is Grandthum Phase IV?
The register gives no street address for this registration beyond the district, Gautam Buddha Nagar, Uttar Pradesh.
What is the price of Grandthum Phase IV?
This page prints no price. The register carries none, and no dated rate or cost sheet from the promoter is on file with this desk. Ask the desk and you will get whatever is current in writing, or be told it is not available.
Has the completion date of Grandthum Phase IV been extended?
The register lists 4 extension entries for this registration. Each entry, with the register's own reason text, is in the full file on UP-RERA Tracker by Vidastu, linked from this page.
Read from the UP-RERA register on 10 October 2026. Directory: every registration this desk has read.