Filing Brief · Yamuna Expressway / YEIDA

YEIDA BPMS drawing requirements: what the architect files and what Smart-DCR checks

A YEIDA building plan is filed only through the BPMS portal, only by an architect registered with the Council of Architecture and with YEIDA, and only in the CAD format set by the portal’s drawing manual. The Smart-DCR engine pre-checks every drawing against the byelaws and issues a scrutiny report listing each rule parameter; the fee is paid only after that pass, and a scanned copy of the signed, scrutiny-approved drawing is uploaded in place of any hard copy. What the drawing must prove is set by Regulation 24.1, Table 1: coverage, FAR, the 15 m height cap, setbacks and the dwelling-unit cap for the plot’s band.

Sources: YEIDA BPMS portal notice, FAQ and Allottee User Manual 1.0 (bpms.yamunaexpresswayauthority.com, read 2 November 2026), as summarised on our BPMS guide; The Yamuna Expressway Industrial Development Area Building Regulations, 2010, Notification No. 311/77-3-09-8X/09 dated 20 December 2010 (Regulations 10, 13(2), 15, 20.1.1, 20.1.2, 24.1 and 24.8(16)), as transcribed on our regulations page, read 6 October 2026; YEIDA’s 87th board meeting of 7 November 2025, as reported by the Times of India, 8 November 2025. Fee amounts are not printed. The portal’s own screens and checklist govern your file.

Who may draw and file

BPMS accepts a plan only from an architect on its own list. Architects register on the portal with their Council of Architecture number; the allottee logs in with CCP or PMS credentials and picks one from the Selection of Architect list, which shows architects registered with the CoA and with YEIDA. The architect accepts or rejects the request, and the allottee is told by SMS and email. An architect who is not on the portal cannot file, however experienced (BPMS guide).

Before you engage anyone, ask for the CoA registration number and check that the name appears in the portal’s list when you log in. Vidastu files the plan in-house with a Council of Architecture registered architect as part of every build.

The format: CAD, to the portal’s drawing manual

The portal publishes a CAD drawing manual for architects, and the drawing is prepared to it and uploaded. Smart-DCR runs a pre-check; a drawing that passes gets a scrutiny report listing each YEIDA rule parameter, which the architect can fetch online with the Application Reference Number. A drawing that fails goes back to the architect for correction. No hard copy is filed: once the fee is paid, a scanned copy of the duly signed, scrutiny-approved drawing is uploaded.

No source on this site reproduces the manual’s sheet list, so this page does not guess at it. The manual on the portal governs. What every sanction drawing must demonstrate, whatever the sheets, is the set of limits below.

What Smart-DCR checks: the Table 1 limits

ParameterThe rule, residential plotsWhere it comes from
Ground coverageBanded by plot size: 75 per cent up to 300 sqm, 65 per cent above 300 to 500, 60 per cent above 500 to 750, 55 per cent above 750 to 1,250, 50 per cent to 1,750, 45 per cent to 3,500, 40 per cent to 4,000 sqmRegulation 24.1, Table 1
FAR1.80 up to 500 sqm, 1.50 above 500 to 2,000 sqm, 1.00 above 2,000 to 4,000 sqmTable 1
Height15 m on every band, counted from the top of the drain to the top of the building, without exemptionTable 1 and its notes
Front setbackFrom 1.5 m on the smallest plots to 20 m on the largest; for example 3.0 m above 120 to 200 sqm, 3.25 m above 200 to 300 sqm, 4.0 m above 300 to 400 sqmTable 1
Side and rear open spaceA plain side setback only from 500 sqm upward (2.5 m to 6 m); below that a side pocket in front of the ramp from 200 sqm; a minimum rear envelope pocket up to 2,000 sqm and a plain rear width above that. Table 1 defers specific setbacks to the sector zonal planTable 1 and its notes
Dwelling unitsUp to 100 sqm: two plus a servant quarter; above 100 to 500 sqm: three; above 500 sqm: fourRegulation 24.1(2)
Stilt parkingFAR-free up to 2.4 m to beam bottom on plots of 112 sqm and aboveRegulation 24.1(2)
BasementA single basement equal to the ground coverage excluded from FAR when used for parking, services or storage; subject to a structural stability certificateRegulations page; how much can I build guide
BalconiesUp to 1.5 m wide excluded from FAR; a wider balcony counts one fourth of its area; enclosure of any kind prohibited and not compoundableRegulation 24.8(16)
Canopy and rampsCanopy projections up to 4.5 m by 2.4 m in front or side setbacks where the front setback is 4.5 m or more; open vehicle ramps in the side setback onlyHow much can I build guide

From Regulation 24.1, Table 1 and Regulations 24.1(2) and 24.8(16) of the YEIDA Building Regulations 2010, as transcribed on our regulations page and gathered on YEIDA plot construction rules. Smart-DCR checks against YEIDA’s current rules and amendments, which can differ from the 2010 table; the scrutiny report for your file is the authority.

What the architect needs from you before drawing

A structural design and the engineer’s stability certificate are listed in our guides for basements and for the completion stage; confirm on the portal whether your file asks for them at sanction.

Why drawings fail scrutiny

After the sanction, the drawing becomes the standard the house is checked against at completion: the empanelled architect certifies that the built structure matches the sanctioned naksha, and YEIDA inspects (completion certificate guide). The sanction is valid for 5 years. How to follow the file after upload is on checking your BPMS application status. This page prints no fee or price; the portal shows the fee for your file, and the desk quotes the build after a site walk.

Related guides

BPMS drawing requirements: frequently asked questions

What format does a YEIDA BPMS building plan drawing have to be in?
The architect prepares the drawing in the CAD format set by the portal’s drawing manual and uploads it on BPMS. Smart-DCR pre-checks it; once it passes and the fee is paid, a scanned copy of the duly signed, scrutiny-approved drawing is uploaded. No hard copy is filed.
Who can prepare and file the drawing?
Only an architect registered with the Council of Architecture and with YEIDA, chosen from the portal’s Selection of Architect list after the allottee logs in with CCP or PMS credentials. The architect accepts the request, and the allottee is told by SMS and email.
What does Smart-DCR check on a YEIDA drawing?
The drawing against YEIDA’s rules: for a residential plot, the Table 1 limits for its band (ground coverage, FAR, the 15 m height cap, setbacks), the dwelling-unit cap, and exclusions such as stilt parking, a single basement and balconies up to 1.5 m. Every drawing that passes gets a scrutiny report listing each rule parameter.
What does my architect need from me before drawing?
The allotment letter (plot area, sector, category), the YEIDA-issued site plan (frontage and depth), the sector zonal plan for setbacks, a clear dues position on PIMS, your CCP or PMS login with its registered mobile and email, and the brief: floors, rooms, parking, basement, and whether the house is built in phases to meet the certificate first.
Why do YEIDA drawings fail scrutiny?
Coverage, FAR or height over the band; setbacks that do not match the sector zonal plan; an enclosed balcony, which is prohibited and not compoundable; a file not in the portal’s CAD format; or a plan filed with the wrong authority. A failed drawing goes back to the architect for correction and resubmission.
Is the sanctioned drawing used again later?
Yes. At completion the empanelled architect certifies that the built house matches the sanctioned naksha, and YEIDA inspects against it. A house that departs from the drawing is the first ground on which a completion certificate is refused. The sanction is valid for 5 years.

Talk to the construction desk

Need the drawing filed? We line up the architect.

Send your sector, plot size and the floors you want. We confirm what fits in your band, line up the Council of Architecture registered architect, file on BPMS, and put one binding, itemised fixed quote in writing after a free site walk.

Call +91 95404 45300

Your number goes to the construction desk, not a call-centre.

By submitting you consent to be contacted about your enquiry. Nothing is auto-sent; no payment is ever requested online.

Disclaimer: Vidastu Advisory (UP-RERA Agent UPRERAAGT000309/01/2026) is the RERA-registered agent desk. Vidastu Developers Pvt. Ltd., the construction entity on this page, is not itself RERA-registered and files and executes YEIDA building plans as a contractor. YEIDA alone sanctions building plans and issues the completion and occupancy certificate. Portal steps are as described in the BPMS portal’s FAQ and Allottee User Manual as read on the dates stated; YEIDA revises the portal, its fees and its checklists. Regulation figures are from the YEIDA Building Regulations 2010 as transcribed on this site. Your allotment letter, lease deed and the portal’s own screens govern your own file. General guidance, not legal advice.