Scheme terms · Clause 14, Period of construction

YEIDA extension charges: what an unbuilt plot costs once the construction period ends

YEIDA gives a residential allottee three years from the lease deed to build and obtain the occupancy certificate. After that, more time is granted only against extension charges: 4 per cent of the plot’s total premium for the first year, 5 per cent for the second and 6 per cent for the third, then 4 per cent of the prevailing sector rate per sq m a year. That is clause 14 of the scheme brochure, printed the same way from RPS-02/2015 to RPS-10/2026. On a 200 sqm RPS-10/2026 plot the first three years come to ₹10,87,800 at the brochure’s own rate of ₹36,260 per sq m.

Sources: YEIDA residential plot scheme brochures, clause 14 “Period of construction” and clause 22 “Execution of lease deed”, each read on 15 November 2026 from the Authority’s own website: RPS-10/2026, RPS-08(A)/2024, RPS-08/2024, RPS-07/2023, RPS-06/2022, RPS-05/2021, RPS-03/2016, RPS-02/2015 (the last two are in Hindi); Regulation 13(5) of The Yamuna Expressway Industrial Development Area Building Regulations, 2010 (Notification No. 311/77-3-09-8X/09 dated 20 December 2010); YEIDA’s 87th board meeting of 7 November 2025, as reported by the Times of India, 8 November 2025. Rupee figures are our arithmetic on the rate each brochure prints. Your allotment letter and lease deed govern your own plot.

What does YEIDA charge when a plot is not built in time?

One clause sets it, and YEIDA has printed that clause the same way in every residential plot brochure we could open, from 2015 to 2026.

Clause 14, “Period of construction”, RPS-10/2026 brochure. “The Allottee/ Lessee will have to complete the construction as per YEIDA building regulations and obtain occupancy certificate from the Authority within three years from date of execution of Lease Deed. In case the Lessee does not construct the building within prescribed time period, the extension of time can be granted on payment of extension charges at the following rates.” The clause then lists four rates:
  • 4% of the total premium of the plot for the first year
  • 5% of the total premium of the plot for the second year
  • 6% of the total premium of the plot for the third year
  • beyond three years, 4% of the sector rate per sq m, per year, at the rate prevailing when the extension is granted

Three things follow from the wording. The clock starts at the lease deed, not at the draw or the allotment letter. What stops it is the occupancy certificate, not a structure and not an application. And the charge is counted on the plot’s total premium for three years, then on YEIDA’s own sector rate. No brochure we read counts it on the circle rate.

Read from the RPS-10/2026 brochure (scheme code RPS10/2026, UP-RERA registration UPRERAPRJ307764/03/2026), clause 14, PDF page 7, on 15 November 2026. The page is an image, so the text above is our transcription, checked against the page by eye.

Is the clause the same for every YEIDA scheme?

For the eight brochures YEIDA’s website still serves, yes on the rates. The two oldest add a condition on how much must be built.

Scheme and brochureBrochure coverTime to buildExtension charges
RPS-10/2026
Clause 14, PDF page 7
Sectors 15C, 18 and 24A; draw 18 June 20263 years from the date the lease deed is executed, with the occupancy certificate in handYears 1 to 3: 4%, 5% and 6% of the plot’s total premium. After that: 4% of the sector rate per sq m, per year, at the rate prevailing when the extension is granted
RPS-08(A)/2024
Clause 14, PDF page 7
Sector 24A; draw 27 December 20243 years from the date the lease deed is executed, with the occupancy certificate in handYears 1 to 3: 4%, 5% and 6% of the plot’s total premium. After that: 4% of the sector rate per sq m, per year, at the rate prevailing when the extension is granted
RPS-08/2024
Clause 14, PDF page 6
Sectors 16, 18, 20 and 22D; draw 20 September 20243 years from the date the lease deed is executed, with the occupancy certificate in handYears 1 to 3: 4%, 5% and 6% of the plot’s total premium. After that: 4% of the sector rate per sq m, per year, at the rate prevailing when the extension is granted
RPS-07/2023
Clause 14, PDF page 7
Sectors 16, 17 and 20; draw 18 October 20233 years from the date the lease deed is executed, with the occupancy certificate in handYears 1 to 3: 4%, 5% and 6% of the plot’s total premium. After that: 4% of the sector rate per sq m, per year, at the rate prevailing when the extension is granted
RPS-06/2022
Clause 14, PDF page 6
Sectors 16, 17, 18, 20 and 22D; draw 18 November 20223 years from the date the lease deed is executed, with the occupancy certificate in handYears 1 to 3: 4%, 5% and 6% of the plot’s total premium. After that: 4% of the sector rate per sq m, per year, at the rate prevailing when the extension is granted
RPS-05/2021
Clause 14, PDF page 6
Sectors 16, 17, 18, 20 and 22D; draw 10 March 20223 years from the date the lease deed is executed, with the occupancy certificate in handYears 1 to 3: 4%, 5% and 6% of the plot’s total premium. After that: 4% of the sector rate per sq m prevailing when the extension is granted (the words “per year” are not printed)
RPS-03/2016
Clause 14, PDF pages 3 and 4
Brochure in Hindi3 years from the due date for executing the lease deed, with 50% of the maximum permissible FAR built and the completion certificate in handYears 1 to 3: 4%, 5% and 6% of the plot’s total premium. After that: 4% of the plot rate per sq m prevailing when the extension is granted
RPS-02/2015
Clause 14, PDF page 4
Brochure in Hindi3 years from the due date for executing the lease deed, with 50% of the maximum permissible FAR built and the occupancy certificate in handYears 1 to 3: 4%, 5% and 6% of the plot’s total premium. After that: 4% of the plot rate per sq m prevailing when the extension is granted

Each scheme name links the brochure PDF on yamunaexpresswayauthority.com, listed on YEIDA’s residential plots page and scheme archive; all eight read on 15 November 2026. Sectors and draw dates are from each brochure’s cover. Two schemes could not be read: the link to the Residential Plot Scheme 2009 brochure on YEIDA’s page did not open on that date, and no RPS-09/2025 brochure is in the archive list. Allottees of those two schemes should read the construction clause in their own lease deed.

What does that come to in rupees?

The charge is a percentage of the plot’s total premium, so it scales with the rate your scheme was sold at. Clause 4 of each brochure prints that rate. Per square metre of plot, the three years work out as follows.

SchemeRate per sq m (clause 4)Year 1, per sq mYear 2, per sq mYear 3, per sq m
RPS-10/2026₹36,260₹1,450.40₹1,813₹2,175.60
RPS-08/2024 and RPS-08(A)/2024₹25,900₹1,036₹1,295₹1,554
RPS-07/2023₹24,600₹984₹1,230₹1,476
RPS-06/2022₹18,510₹740.40₹925.50₹1,110.60
RPS-05/2021, plots of 120 to 200 sqm₹17,800₹712₹890₹1,068
RPS-05/2021, plots above 200 sqm₹17,400₹696₹870₹1,044

Rates as printed in clause 4 of each scheme brochure, read on 15 November 2026. The yearly figures are 4%, 5% and 6% of that rate: our arithmetic. Multiply by your plot area for the yearly charge, before any location charge.

Worked for the six plot sizes of RPS-10/2026, at the brochure’s rate of ₹36,260 per sq m (clause 4, brochure dated 4 April 2026):

Plot size and plots in the schemePremium at the scheme rateYear 1 (4%)Year 2 (5%)Year 3 (6%)Three years together
162 sqm
476 plots
₹58,74,120₹2,34,965₹2,93,706₹3,52,447₹8,81,118
183 sqm
4 plots
₹66,35,580₹2,65,423₹3,31,779₹3,98,135₹9,95,337
184 sqm
4 plots
₹66,71,840₹2,66,874₹3,33,592₹4,00,310₹10,00,776
200 sqm
481 plots
₹72,52,000₹2,90,080₹3,62,600₹4,35,120₹10,87,800
223 sqm
6 plots
₹80,85,980₹3,23,439₹4,04,299₹4,85,159₹12,12,897
290 sqm
2 plots
₹1,05,15,400₹4,20,616₹5,25,770₹6,30,924₹15,77,310

Plot sizes and counts from the brochure’s table 1(A), “Details of total vacant plots” (973 plots in all). Premium is plot area multiplied by the clause 4 rate; the charges are our arithmetic on it. Clause 2.1 adds preference location charges of 5% of the premium each for a park-facing or green-belt plot, a corner plot and a road of 18 m or more, capped at 15%. Your allotment letter states your plot’s own premium, and that figure governs.

After the third year. The basis changes from your premium to the sector rate in force when YEIDA grants the extension. As an illustration only: if that rate were the RPS-10/2026 figure of ₹36,260 per sq m, 4% would be ₹1,450.40 per sq m a year, or ₹2,90,080 a year on a 200 sqm plot. YEIDA revises its rates, so the real figure is the one in force on the day of the grant.

Where does 31 December 2026 fit?

YEIDA’s 87th board meeting on 7 November 2025 let residential allottees whose lease deed is executed, but whose house is not built, complete construction without extension charges until 31 December 2026, as the Times of India reported the next day. It is a pause on clause 14, not a change to it.

The full plan for the date, stage by stage, is on our 31 December 2026 deadline guide.

Is there a charge for executing the lease deed late?

Yes, and it is a separate clock. Clause 22 of the same brochures covers it.

Clause 22 read on 15 November 2026 in the RPS-10/2026, RPS-08(A)/2024, RPS-08/2024, RPS-07/2023, RPS-06/2022 and RPS-05/2021 brochures. The steps themselves are on lease deed after allotment.

Does applying for the certificate stop the charges?

No. Clause 14 asks for the certificate itself. The Building Regulations also penalise an early application: under Regulation 13(5), when an allottee applies for the occupancy certificate without actually completing the building, the inspection is done within 30 days, and a building found incomplete is penalised 50% of the occupancy charges or Rs 5,000, whichever is more. The application is rejected, and the allottee applies afresh “along with penalty charges and time extension charges if required”.

What counts as complete is in Regulation 24.1(2)(x): at least 40 sqm or 50 per cent of the maximum permissible ground coverage, whichever is more, with a functional toilet or bath and a kitchen. The completion certificate guide sets out the rest. Allottees under the 2015 and 2016 brochures should also read their lease deed for the 50% of FAR condition in the table above.

Regulation 13(5) read on 15 November 2026 in YEIDA’s copy of the 2010 Regulations; YEIDA also publishes it on its own as the timeline for sanction or refusal of a building permit.

How do you keep the charge as small as possible?

  1. Find your dates. Lease deed execution date, plus three years, is your clause 14 date. If the 31 December 2026 window covers you, that is your date instead.
  2. Get your account position from YEIDA in writing. Dues, any extension already charged, and the premium figure the charge is counted on.
  3. Get the map sanctioned first. Work cannot start before the sanction on YEIDA’s BPMS portal, and a house built without one cannot be certified. How the BPMS sanction works.
  4. Build the qualifying block and lodge early. The certificate needs the Regulation 24.1(2)(x) minimum, not the whole house. The Authority has up to 90 days to decide a completion application (Regulation 20.1.1), so the day you lodge matters.
  5. Finish the remaining floors under the same sanctioned plan. A sanction is valid for five years.
Related guides

YEIDA extension charges: questions allottees ask

What are YEIDA’s extension charges for not building on a residential plot?
Under clause 14 of the scheme brochure, 4 per cent of the plot’s total premium for the first year of extension, 5 per cent for the second and 6 per cent for the third. Beyond three years it is 4 per cent of the sector rate per sq m, per year, at the rate prevailing when the extension is granted. The eight residential brochures on YEIDA’s website, from RPS-02/2015 to RPS-10/2026, all print these rates.
How much is the YEIDA extension charge on a 200 sqm plot?
For an RPS-10/2026 plot, the brochure rate of ₹36,260 per sq m gives a premium of ₹72,52,000 on 200 sqm before any location charge. The first year of extension is then ₹2,90,080, the second ₹3,62,600 and the third ₹4,35,120, which is ₹10,87,800 over three years. This is our arithmetic on the brochure’s rate; the premium on your allotment letter governs.
Is the YEIDA late construction penalty charged on the circle rate?
No brochure we read says so. Clause 14 counts the charge on the plot’s total premium for the first three years and on YEIDA’s own sector rate after that. The circle rate is the district administration’s valuation list for stamp duty, a different instrument.
Do I pay extension charges after 31 December 2026?
If your lease deed is executed and your three years are over, the no-charge window from YEIDA’s 87th board meeting closes on 31 December 2026. Without the certificate by then, further time is granted against extension charges at your scheme’s rates. Which year of extension an older plot is counted in from 1 January 2027 is not stated in the documents we could read, so ask YEIDA for your account position in writing.
I won a plot in RPS-10/2026. When do extension charges start for me?
Three years after your lease deed is executed, if the occupancy certificate is not in hand by then (clause 14). Nothing falls due on 31 December 2026. The brochure also says possession will be handed over after five years from the issue of the allotment letter (clause 22(i)), and gives 90 days from the checklist to complete the lease deed (clause 22(iii)).
Does applying for the completion certificate stop the charges?
No. Clause 14 asks for the occupancy certificate itself. Under Regulation 13(5) of the YEIDA Building Regulations 2010, an application made before the building is actually complete is rejected with a penalty of 50 per cent of the occupancy charges or Rs 5,000, whichever is more, and the allottee applies again with any time extension charges due.
What does YEIDA charge for executing the lease deed late?
Clause 22(iii) of the brochures gives a fixed time after the checklist is issued: 90 days in RPS-10/2026, and 180 days in RPS-07/2023, RPS-08/2024 and RPS-08(A)/2024. Beyond that the extension costs 1 per cent of the total premium for the first year and 2 per cent for the second, paid quarterly. After two years the brochure says the penalty follows YEIDA’s prevailing policy.
Which YEIDA schemes does this page not cover?
The Residential Plot Scheme 2009, whose brochure link on YEIDA’s residential plots page did not open on 15 November 2026, and RPS-09/2025, whose brochure is not in YEIDA’s archive list. Allottees of those schemes should read the construction clause in their own lease deed. Industrial, commercial and group housing plots follow their own scheme terms.

Talk to the construction desk

Know your date, then build to the certificate

Send your sector, plot size and lease-deed date. We work out where your construction period stands, what the certificate minimum is on your plot, and give one binding, itemised fixed quote after a free site walk.

Call +91 95404 45300

Your number goes to the construction desk, not a call-centre.

By submitting you consent to be contacted about your enquiry. Nothing is auto-sent; no payment is ever requested online.

Disclaimer: Vidastu Advisory (UP-RERA Agent UPRERAAGT000309/01/2026) is the RERA-registered agent desk. Vidastu Developers Pvt. Ltd., the construction entity on this page, is not itself RERA-registered and files and executes YEIDA building plans as a contractor. Clauses are quoted from YEIDA’s scheme brochures and the YEIDA Building Regulations 2010 as read on 15 November 2026; brochures that are images were transcribed by us. Rupee figures are our own arithmetic on the brochure rates and are not a demand, an estimate of your dues or a statement by YEIDA. YEIDA alone grants time extensions and fixes what is payable. Your allotment letter, lease deed and YEIDA’s written account statement govern your own plot. General guidance, not legal advice.