What does YEIDA charge when a plot is not built in time?
One clause sets it, and YEIDA has printed that clause the same way in every residential plot brochure we could open, from 2015 to 2026.
- 4% of the total premium of the plot for the first year
- 5% of the total premium of the plot for the second year
- 6% of the total premium of the plot for the third year
- beyond three years, 4% of the sector rate per sq m, per year, at the rate prevailing when the extension is granted
Three things follow from the wording. The clock starts at the lease deed, not at the draw or the allotment letter. What stops it is the occupancy certificate, not a structure and not an application. And the charge is counted on the plot’s total premium for three years, then on YEIDA’s own sector rate. No brochure we read counts it on the circle rate.
Read from the RPS-10/2026 brochure (scheme code RPS10/2026, UP-RERA registration UPRERAPRJ307764/03/2026), clause 14, PDF page 7, on 15 November 2026. The page is an image, so the text above is our transcription, checked against the page by eye.
Is the clause the same for every YEIDA scheme?
For the eight brochures YEIDA’s website still serves, yes on the rates. The two oldest add a condition on how much must be built.
| Scheme and brochure | Brochure cover | Time to build | Extension charges |
|---|---|---|---|
| RPS-10/2026 Clause 14, PDF page 7 | Sectors 15C, 18 and 24A; draw 18 June 2026 | 3 years from the date the lease deed is executed, with the occupancy certificate in hand | Years 1 to 3: 4%, 5% and 6% of the plot’s total premium. After that: 4% of the sector rate per sq m, per year, at the rate prevailing when the extension is granted |
| RPS-08(A)/2024 Clause 14, PDF page 7 | Sector 24A; draw 27 December 2024 | 3 years from the date the lease deed is executed, with the occupancy certificate in hand | Years 1 to 3: 4%, 5% and 6% of the plot’s total premium. After that: 4% of the sector rate per sq m, per year, at the rate prevailing when the extension is granted |
| RPS-08/2024 Clause 14, PDF page 6 | Sectors 16, 18, 20 and 22D; draw 20 September 2024 | 3 years from the date the lease deed is executed, with the occupancy certificate in hand | Years 1 to 3: 4%, 5% and 6% of the plot’s total premium. After that: 4% of the sector rate per sq m, per year, at the rate prevailing when the extension is granted |
| RPS-07/2023 Clause 14, PDF page 7 | Sectors 16, 17 and 20; draw 18 October 2023 | 3 years from the date the lease deed is executed, with the occupancy certificate in hand | Years 1 to 3: 4%, 5% and 6% of the plot’s total premium. After that: 4% of the sector rate per sq m, per year, at the rate prevailing when the extension is granted |
| RPS-06/2022 Clause 14, PDF page 6 | Sectors 16, 17, 18, 20 and 22D; draw 18 November 2022 | 3 years from the date the lease deed is executed, with the occupancy certificate in hand | Years 1 to 3: 4%, 5% and 6% of the plot’s total premium. After that: 4% of the sector rate per sq m, per year, at the rate prevailing when the extension is granted |
| RPS-05/2021 Clause 14, PDF page 6 | Sectors 16, 17, 18, 20 and 22D; draw 10 March 2022 | 3 years from the date the lease deed is executed, with the occupancy certificate in hand | Years 1 to 3: 4%, 5% and 6% of the plot’s total premium. After that: 4% of the sector rate per sq m prevailing when the extension is granted (the words “per year” are not printed) |
| RPS-03/2016 Clause 14, PDF pages 3 and 4 | Brochure in Hindi | 3 years from the due date for executing the lease deed, with 50% of the maximum permissible FAR built and the completion certificate in hand | Years 1 to 3: 4%, 5% and 6% of the plot’s total premium. After that: 4% of the plot rate per sq m prevailing when the extension is granted |
| RPS-02/2015 Clause 14, PDF page 4 | Brochure in Hindi | 3 years from the due date for executing the lease deed, with 50% of the maximum permissible FAR built and the occupancy certificate in hand | Years 1 to 3: 4%, 5% and 6% of the plot’s total premium. After that: 4% of the plot rate per sq m prevailing when the extension is granted |
Each scheme name links the brochure PDF on yamunaexpresswayauthority.com, listed on YEIDA’s residential plots page and scheme archive; all eight read on 15 November 2026. Sectors and draw dates are from each brochure’s cover. Two schemes could not be read: the link to the Residential Plot Scheme 2009 brochure on YEIDA’s page did not open on that date, and no RPS-09/2025 brochure is in the archive list. Allottees of those two schemes should read the construction clause in their own lease deed.
What does that come to in rupees?
The charge is a percentage of the plot’s total premium, so it scales with the rate your scheme was sold at. Clause 4 of each brochure prints that rate. Per square metre of plot, the three years work out as follows.
| Scheme | Rate per sq m (clause 4) | Year 1, per sq m | Year 2, per sq m | Year 3, per sq m |
|---|---|---|---|---|
| RPS-10/2026 | ₹36,260 | ₹1,450.40 | ₹1,813 | ₹2,175.60 |
| RPS-08/2024 and RPS-08(A)/2024 | ₹25,900 | ₹1,036 | ₹1,295 | ₹1,554 |
| RPS-07/2023 | ₹24,600 | ₹984 | ₹1,230 | ₹1,476 |
| RPS-06/2022 | ₹18,510 | ₹740.40 | ₹925.50 | ₹1,110.60 |
| RPS-05/2021, plots of 120 to 200 sqm | ₹17,800 | ₹712 | ₹890 | ₹1,068 |
| RPS-05/2021, plots above 200 sqm | ₹17,400 | ₹696 | ₹870 | ₹1,044 |
Rates as printed in clause 4 of each scheme brochure, read on 15 November 2026. The yearly figures are 4%, 5% and 6% of that rate: our arithmetic. Multiply by your plot area for the yearly charge, before any location charge.
Worked for the six plot sizes of RPS-10/2026, at the brochure’s rate of ₹36,260 per sq m (clause 4, brochure dated 4 April 2026):
| Plot size and plots in the scheme | Premium at the scheme rate | Year 1 (4%) | Year 2 (5%) | Year 3 (6%) | Three years together |
|---|---|---|---|---|---|
| 162 sqm 476 plots | ₹58,74,120 | ₹2,34,965 | ₹2,93,706 | ₹3,52,447 | ₹8,81,118 |
| 183 sqm 4 plots | ₹66,35,580 | ₹2,65,423 | ₹3,31,779 | ₹3,98,135 | ₹9,95,337 |
| 184 sqm 4 plots | ₹66,71,840 | ₹2,66,874 | ₹3,33,592 | ₹4,00,310 | ₹10,00,776 |
| 200 sqm 481 plots | ₹72,52,000 | ₹2,90,080 | ₹3,62,600 | ₹4,35,120 | ₹10,87,800 |
| 223 sqm 6 plots | ₹80,85,980 | ₹3,23,439 | ₹4,04,299 | ₹4,85,159 | ₹12,12,897 |
| 290 sqm 2 plots | ₹1,05,15,400 | ₹4,20,616 | ₹5,25,770 | ₹6,30,924 | ₹15,77,310 |
Plot sizes and counts from the brochure’s table 1(A), “Details of total vacant plots” (973 plots in all). Premium is plot area multiplied by the clause 4 rate; the charges are our arithmetic on it. Clause 2.1 adds preference location charges of 5% of the premium each for a park-facing or green-belt plot, a corner plot and a road of 18 m or more, capped at 15%. Your allotment letter states your plot’s own premium, and that figure governs.
Where does 31 December 2026 fit?
YEIDA’s 87th board meeting on 7 November 2025 let residential allottees whose lease deed is executed, but whose house is not built, complete construction without extension charges until 31 December 2026, as the Times of India reported the next day. It is a pause on clause 14, not a change to it.
- Lease deed executed, three years already over. The no-charge window closes on 31 December 2026. Without the certificate by then, more time means extension charges at your scheme’s rates. Which year of extension an older plot is counted in from 1 January 2027 is not stated in any document we could read, so ask YEIDA for your account position in writing.
- Lease deed executed, three years still running. Your own clause 14 date governs. Check the execution date on the deed and count three years.
- Plot won in RPS-10/2026 or another recent draw, no lease deed yet. Nothing falls due on 31 December 2026. Your three years begin on the day your lease deed is executed.
The full plan for the date, stage by stage, is on our 31 December 2026 deadline guide.
Is there a charge for executing the lease deed late?
Yes, and it is a separate clock. Clause 22 of the same brochures covers it.
- Possession. Clause 22(i) of the RPS-10/2026 brochure says possession of the allotted plot “will be handed over after five years from issue of allotment letter”. The RPS-05/2021, RPS-06/2022, RPS-08/2024 and RPS-08(A)/2024 brochures say the same; RPS-07/2023 says three years.
- Once possession is offered. The allottee has 180 days from the offer to execute and register the lease deed and take possession. Missing that brings administrative charges of 1% of the total premium for a one-year extension. Missing the extended date as well brings “action for cancellation of allotment and forfeiture of deposited money” (clause 22(ii)).
- Once the checklist is issued. Clause 22(iii) gives 90 days in RPS-10/2026, and 180 days in RPS-07/2023, RPS-08/2024 and RPS-08(A)/2024, to complete the lease deed. Beyond that, the extension costs 1% of the total premium for the first year and 2% for the second, paid quarterly. After two years, in the brochure’s words, “the penalty will be given under prevailing policy of YEIDA”.
Clause 22 read on 15 November 2026 in the RPS-10/2026, RPS-08(A)/2024, RPS-08/2024, RPS-07/2023, RPS-06/2022 and RPS-05/2021 brochures. The steps themselves are on lease deed after allotment.
Does applying for the certificate stop the charges?
No. Clause 14 asks for the certificate itself. The Building Regulations also penalise an early application: under Regulation 13(5), when an allottee applies for the occupancy certificate without actually completing the building, the inspection is done within 30 days, and a building found incomplete is penalised 50% of the occupancy charges or Rs 5,000, whichever is more. The application is rejected, and the allottee applies afresh “along with penalty charges and time extension charges if required”.
What counts as complete is in Regulation 24.1(2)(x): at least 40 sqm or 50 per cent of the maximum permissible ground coverage, whichever is more, with a functional toilet or bath and a kitchen. The completion certificate guide sets out the rest. Allottees under the 2015 and 2016 brochures should also read their lease deed for the 50% of FAR condition in the table above.
Regulation 13(5) read on 15 November 2026 in YEIDA’s copy of the 2010 Regulations; YEIDA also publishes it on its own as the timeline for sanction or refusal of a building permit.
How do you keep the charge as small as possible?
- Find your dates. Lease deed execution date, plus three years, is your clause 14 date. If the 31 December 2026 window covers you, that is your date instead.
- Get your account position from YEIDA in writing. Dues, any extension already charged, and the premium figure the charge is counted on.
- Get the map sanctioned first. Work cannot start before the sanction on YEIDA’s BPMS portal, and a house built without one cannot be certified. How the BPMS sanction works.
- Build the qualifying block and lodge early. The certificate needs the Regulation 24.1(2)(x) minimum, not the whole house. The Authority has up to 90 days to decide a completion application (Regulation 20.1.1), so the day you lodge matters.
- Finish the remaining floors under the same sanctioned plan. A sanction is valid for five years.
- 31 December 2026 deadline: who it covers and the plan for each stage.
- YEIDA completion certificate: the document that ends the clock.
- Lease deed after allotment: the step that starts it.
- YEIDA building plan approval on BPMS: the sanction before any work.
- YEIDA plot construction rules: coverage, FAR, height and setbacks.
- Construction cost guide and the quote checker.