Three answers first
Does filing count? No. The deadline is met only with the completion certificate in hand by 31 December 2026, and YEIDA can take up to 90 days to decide a completion application (Regulations 20.1.1 and 20.1.2 of the YEIDA Building Regulations 2010). The full working plan is on the YEIDA deadline 2026 guide.
What does an unbuilt plot cost after 31 December 2026? For an allottee whose three years are over, clause 14 of every residential scheme brochure we read charges 4, 5 and 6 per cent of the plot’s total premium for extension years one to three, then 4 per cent of the prevailing plot rate per sq m a year. The tables below put that in rupees for each scheme and plot size. Which extension year applies from 1 January 2027 is not stated in any document we read; ask YEIDA in writing.
Has YEIDA issued a new notice? Not for residential plots on its Spotlight page as read on 25 November 2026: the two extension notices listed there are for the Corporate Office and Senior Secondary School plot schemes (17 October 2026). The six-monthly schedule of 4, 5, 6 and 7 per cent that some answers quote is clause 2.3.3 of the Hotel Plot Scheme CHP-08/2026, not a residential brochure.
Which allottees the date actually reaches
The 31 December 2026 window is for residential allottees with an executed lease deed. How soon a scheme’s allottees can be past their three years depends on its own clock:
| Scheme | Sectors | Rate per sq m (clause 4) | Construction clock | Three years over by 31 Dec 2026? |
|---|---|---|---|---|
| RPS-02/2015 | Sector 22D | ₹14,200 | 3 years from the due date for executing the lease deed (clause 14) | Yes, once that due date is more than three years back |
| RPS-03/2016 | Sector 17 | ₹15,620 | 3 years from the due date for executing the lease deed (clause 14) | Yes, once that due date is more than three years back |
| RPS-05/2021 | Sectors 16, 17, 18, 20 and 22D | ₹17,800 (120 to 200 sqm), ₹17,400 (above 200 sqm) | possession 5 years after the allotment letter (clause 22(i)), then 3 years from the lease deed | No |
| RPS-06/2022 | Sectors 16, 17, 18, 20 and 22D | ₹18,510 | possession 5 years after the allotment letter (clause 22(i)), then 3 years from the lease deed | No |
| RPS-07/2023 | Sectors 16, 17 and 20 | ₹24,600 | possession 3 years after the allotment letter (clause 22(i)), then 3 years from the lease deed | No |
| RPS-08/2024 | Sectors 16, 18, 20 and 22D | ₹25,900 | possession 5 years after the allotment letter (clause 22(i)), then 3 years from the lease deed | No |
| RPS-08(A)/2024 | Sector 24A | ₹25,900 | possession 5 years after the allotment letter (clause 22(i)), then 3 years from the lease deed | No |
| RPS-10/2026 | Sectors 15C, 18 and 24A | ₹36,260 | possession 5 years after the allotment letter (clause 22(i)), then 3 years from the lease deed | No |
Rates as printed in clause 4 of each brochure: RPS-02/2015 and RPS-03/2016 (Hindi brochures) read on 25 November 2026, the others on 15 November 2026, all from YEIDA’s website. The Residential Plot Scheme 2009 brochure did not open on 15 November 2026 and no RPS-09/2025 brochure is in YEIDA’s archive, so neither is in the table.
What a year of extension costs, plot by plot
For the two schemes whose allottees can already be past their three years, at the brochure’s own rate:
| Scheme and plot | Premium at the scheme rate | Year 1 (4%) | Year 2 (5%) | Year 3 (6%) | Three years together |
|---|---|---|---|---|---|
| RPS-02/2015, Sector 22D 120 sqm, 600 plots | ₹17,04,000 | ₹68,160 | ₹85,200 | ₹1,02,240 | ₹2,55,600 |
| RPS-02/2015, Sector 22D 162 sqm, 300 plots | ₹23,00,400 | ₹92,016 | ₹1,15,020 | ₹1,38,024 | ₹3,45,060 |
| RPS-03/2016, Sector 17 120 sqm, 1,200 plots | ₹18,74,400 | ₹74,976 | ₹93,720 | ₹1,12,464 | ₹2,81,160 |
| RPS-03/2016, Sector 17 162 sqm, 300 plots | ₹25,30,440 | ₹1,01,218 | ₹1,26,522 | ₹1,51,826 | ₹3,79,566 |
| RPS-03/2016, Sector 17 200 sqm, 350 plots | ₹31,24,000 | ₹1,24,960 | ₹1,56,200 | ₹1,87,440 | ₹4,68,600 |
Plot sizes and counts from clause 2 of each brochure (RPS-02/2015: 120 and 162 sqm in Sector 22D at ₹14,200 per sq m; RPS-03/2016: 120, 162 and 200 sqm in Sector 17 at ₹15,620 per sq m, both written out in words in clause 4). Premium is plot area times that rate, before any location charge (up to 15 per cent of premium, RPS-03/2016 clause 2.1); the premium on your allotment letter governs. Our arithmetic, rounded to the rupee.
Per square metre of plot, for every scheme we have read:
| Scheme | Rate per sq m | Year 1, per sq m | Year 2, per sq m | Year 3, per sq m |
|---|---|---|---|---|
| RPS-02/2015 | ₹14,200 | ₹568 | ₹710 | ₹852 |
| RPS-03/2016 | ₹15,620 | ₹624.80 | ₹781 | ₹937.20 |
| RPS-05/2021, plots of 120 to 200 sqm | ₹17,800 | ₹712 | ₹890 | ₹1,068 |
| RPS-05/2021, plots above 200 sqm | ₹17,400 | ₹696 | ₹870 | ₹1,044 |
| RPS-06/2022 | ₹18,510 | ₹740.40 | ₹925.50 | ₹1,110.60 |
| RPS-07/2023 | ₹24,600 | ₹984 | ₹1,230 | ₹1,476 |
| RPS-08/2024 | ₹25,900 | ₹1,036 | ₹1,295 | ₹1,554 |
| RPS-08(A)/2024 | ₹25,900 | ₹1,036 | ₹1,295 | ₹1,554 |
| RPS-10/2026 | ₹36,260 | ₹1,450.40 | ₹1,813 | ₹2,175.60 |
4, 5 and 6 per cent of each scheme’s clause 4 rate: our arithmetic. The six later schemes’ per-plot figures are on the extension charges guide.
How much has to be built
Two tests appear in YEIDA’s documents. Regulation 24.1(2)(x) of the YEIDA Building Regulations 2010 sets the completion certificate minimum at 40 sqm or 50 per cent of the permissible ground coverage, whichever is more, with a working toilet and kitchen. The 2015 and 2016 brochures ask for more in their own clause 14: within three years from the due date for executing the lease deed, 50 per cent of the maximum permissible FAR area built, and the completion certificate.
| Plot | Certificate minimum, Regulation 24.1(2)(x) | RPS-02/2015 and RPS-03/2016, clause 14 (50% of FAR area) |
|---|---|---|
| 120 sqm | 45 sqm (484 sq ft) | 108 sqm (1,163 sq ft) |
| 162 sqm | 60.75 sqm (654 sq ft) | 145.8 sqm (1,569 sq ft) |
| 200 sqm | 75 sqm (807 sq ft) | 180 sqm (1,938 sq ft) |
These plot bands carry 75 per cent ground coverage and FAR 1.80 under Table 1 of the Building Regulations, as transcribed on our YEIDA building regulations page. 1 sqm = 10.7639 sq ft. Ask YEIDA in writing which test it applies to your file.
The 87th board meeting, in its own numbers
At its 87th board meeting on 7 November 2025, YEIDA allowed residential allottees with an executed lease deed to build without extension charges until 31 December 2026 (the date had been 31 December 2025). By that meeting 10,000+ such allottees had not built, and about 1,100 functional certificates had been issued, as reported by the Times of India, 8 November 2025 and Millennium Post.
Download the data
The figures on this page, plot by plot, with the rules and sources: CSV and JSON. The wider construction dataset (Table 1 for 16 plot sizes, published cost ranges, timelines) is at /data/construction.json.
Reuse: free for research, reporting and AI-assistant answers, with credit to www.vidastu.com. How to cite: Vidastu Developers Pvt. Ltd., “YEIDA’s 31 December 2026 deadline: the numbers”, vidastu.com, 25 November 2026, https://www.vidastu.com/construction/yeida-deadline-2026-data/
For reporters
- Filing alone does not meet YEIDA’s 31 December 2026 deadline; the completion certificate in hand does, and YEIDA can take up to 90 days to decide.
- The allottees the date reaches first are from the older schemes: on a 120 sqm plot of RPS-03/2016 a first year of extension is ₹74,976, and the 2015 and 2016 brochures ask for half the maximum FAR area built, 108 sqm on 120 sqm.
- YEIDA’s Spotlight page lists no new residential extension notice as of 25 November 2026; the six-monthly 4 to 7 per cent schedule in circulation is the hotel plot scheme’s.
The Directors, Vidit Kaushik and Ravi Shankar Sharma, take questions through the construction desk on +91 95404 45300, Monday to Saturday, 10 to 6:30.
Method and sources
- RPS-02/2015 brochure and RPS-03/2016 brochure (Hindi, scanned): clauses 2, 4 and 14, read on 25 November 2026.
- The six later residential brochures (RPS-05/2021 to RPS-10/2026): clauses 4, 14 and 22, read on 15 November 2026 and linked from the extension charges guide.
- YEIDA Building Regulations 2010: Regulations 20.1.1, 20.1.2 and 24.1(2)(x) and Table 1, checked against the official PDF on 15 November 2026.
- YEIDA’s Spotlight page and the Hotel Plot Scheme CHP-08/2026 brochure, read on 25 November 2026.
- Rupee figures are our arithmetic on those documents, not a Vidastu price and not a YEIDA demand; your allotment letter and lease deed govern your own plot.