YEIDA’s 31 December 2026 deadline: the numbers, scheme by scheme

Filing the completion application does not meet the deadline; the certificate in hand does, and YEIDA can take up to 90 days to decide. For an allottee whose three years are over, each year of extension costs 4, 5 and 6 per cent of the plot’s total premium (clause 14): on a 120 sqm plot of the 2016 scheme that is ₹74,976 for a first year, at the brochure’s own rate. Every figure below names the YEIDA document it comes from, read on 25 November 2026.

Sources: YEIDA residential plot scheme brochures RPS-02/2015 and RPS-03/2016 (clauses 2, 4 and 14) read on 25 November 2026, and RPS-05/2021 to RPS-10/2026 read on 15 November 2026; the YEIDA Building Regulations 2010; YEIDA’s 87th board meeting of 7 November 2025 as reported by the Times of India; YEIDA’s Spotlight page, read on 25 November 2026.

Three answers first

Does filing count? No. The deadline is met only with the completion certificate in hand by 31 December 2026, and YEIDA can take up to 90 days to decide a completion application (Regulations 20.1.1 and 20.1.2 of the YEIDA Building Regulations 2010). The full working plan is on the YEIDA deadline 2026 guide.

What does an unbuilt plot cost after 31 December 2026? For an allottee whose three years are over, clause 14 of every residential scheme brochure we read charges 4, 5 and 6 per cent of the plot’s total premium for extension years one to three, then 4 per cent of the prevailing plot rate per sq m a year. The tables below put that in rupees for each scheme and plot size. Which extension year applies from 1 January 2027 is not stated in any document we read; ask YEIDA in writing.

Has YEIDA issued a new notice? Not for residential plots on its Spotlight page as read on 25 November 2026: the two extension notices listed there are for the Corporate Office and Senior Secondary School plot schemes (17 October 2026). The six-monthly schedule of 4, 5, 6 and 7 per cent that some answers quote is clause 2.3.3 of the Hotel Plot Scheme CHP-08/2026, not a residential brochure.

Which allottees the date actually reaches

The 31 December 2026 window is for residential allottees with an executed lease deed. How soon a scheme’s allottees can be past their three years depends on its own clock:

SchemeSectorsRate per sq m (clause 4)Construction clockThree years over by 31 Dec 2026?
RPS-02/2015Sector 22D₹14,2003 years from the due date for executing the lease deed (clause 14)Yes, once that due date is more than three years back
RPS-03/2016Sector 17₹15,6203 years from the due date for executing the lease deed (clause 14)Yes, once that due date is more than three years back
RPS-05/2021Sectors 16, 17, 18, 20 and 22D₹17,800 (120 to 200 sqm), ₹17,400 (above 200 sqm)possession 5 years after the allotment letter (clause 22(i)), then 3 years from the lease deedNo
RPS-06/2022Sectors 16, 17, 18, 20 and 22D₹18,510possession 5 years after the allotment letter (clause 22(i)), then 3 years from the lease deedNo
RPS-07/2023Sectors 16, 17 and 20₹24,600possession 3 years after the allotment letter (clause 22(i)), then 3 years from the lease deedNo
RPS-08/2024Sectors 16, 18, 20 and 22D₹25,900possession 5 years after the allotment letter (clause 22(i)), then 3 years from the lease deedNo
RPS-08(A)/2024Sector 24A₹25,900possession 5 years after the allotment letter (clause 22(i)), then 3 years from the lease deedNo
RPS-10/2026Sectors 15C, 18 and 24A₹36,260possession 5 years after the allotment letter (clause 22(i)), then 3 years from the lease deedNo

Rates as printed in clause 4 of each brochure: RPS-02/2015 and RPS-03/2016 (Hindi brochures) read on 25 November 2026, the others on 15 November 2026, all from YEIDA’s website. The Residential Plot Scheme 2009 brochure did not open on 15 November 2026 and no RPS-09/2025 brochure is in YEIDA’s archive, so neither is in the table.

What a year of extension costs, plot by plot

For the two schemes whose allottees can already be past their three years, at the brochure’s own rate:

Scheme and plotPremium at the scheme rateYear 1 (4%)Year 2 (5%)Year 3 (6%)Three years together
RPS-02/2015, Sector 22D
120 sqm, 600 plots
₹17,04,000₹68,160₹85,200₹1,02,240₹2,55,600
RPS-02/2015, Sector 22D
162 sqm, 300 plots
₹23,00,400₹92,016₹1,15,020₹1,38,024₹3,45,060
RPS-03/2016, Sector 17
120 sqm, 1,200 plots
₹18,74,400₹74,976₹93,720₹1,12,464₹2,81,160
RPS-03/2016, Sector 17
162 sqm, 300 plots
₹25,30,440₹1,01,218₹1,26,522₹1,51,826₹3,79,566
RPS-03/2016, Sector 17
200 sqm, 350 plots
₹31,24,000₹1,24,960₹1,56,200₹1,87,440₹4,68,600

Plot sizes and counts from clause 2 of each brochure (RPS-02/2015: 120 and 162 sqm in Sector 22D at ₹14,200 per sq m; RPS-03/2016: 120, 162 and 200 sqm in Sector 17 at ₹15,620 per sq m, both written out in words in clause 4). Premium is plot area times that rate, before any location charge (up to 15 per cent of premium, RPS-03/2016 clause 2.1); the premium on your allotment letter governs. Our arithmetic, rounded to the rupee.

Per square metre of plot, for every scheme we have read:

SchemeRate per sq mYear 1, per sq mYear 2, per sq mYear 3, per sq m
RPS-02/2015₹14,200₹568₹710₹852
RPS-03/2016₹15,620₹624.80₹781₹937.20
RPS-05/2021, plots of 120 to 200 sqm₹17,800₹712₹890₹1,068
RPS-05/2021, plots above 200 sqm₹17,400₹696₹870₹1,044
RPS-06/2022₹18,510₹740.40₹925.50₹1,110.60
RPS-07/2023₹24,600₹984₹1,230₹1,476
RPS-08/2024₹25,900₹1,036₹1,295₹1,554
RPS-08(A)/2024₹25,900₹1,036₹1,295₹1,554
RPS-10/2026₹36,260₹1,450.40₹1,813₹2,175.60

4, 5 and 6 per cent of each scheme’s clause 4 rate: our arithmetic. The six later schemes’ per-plot figures are on the extension charges guide.

How much has to be built

Two tests appear in YEIDA’s documents. Regulation 24.1(2)(x) of the YEIDA Building Regulations 2010 sets the completion certificate minimum at 40 sqm or 50 per cent of the permissible ground coverage, whichever is more, with a working toilet and kitchen. The 2015 and 2016 brochures ask for more in their own clause 14: within three years from the due date for executing the lease deed, 50 per cent of the maximum permissible FAR area built, and the completion certificate.

PlotCertificate minimum, Regulation 24.1(2)(x)RPS-02/2015 and RPS-03/2016, clause 14 (50% of FAR area)
120 sqm45 sqm (484 sq ft)108 sqm (1,163 sq ft)
162 sqm60.75 sqm (654 sq ft)145.8 sqm (1,569 sq ft)
200 sqm75 sqm (807 sq ft)180 sqm (1,938 sq ft)

These plot bands carry 75 per cent ground coverage and FAR 1.80 under Table 1 of the Building Regulations, as transcribed on our YEIDA building regulations page. 1 sqm = 10.7639 sq ft. Ask YEIDA in writing which test it applies to your file.

The 87th board meeting, in its own numbers

At its 87th board meeting on 7 November 2025, YEIDA allowed residential allottees with an executed lease deed to build without extension charges until 31 December 2026 (the date had been 31 December 2025). By that meeting 10,000+ such allottees had not built, and about 1,100 functional certificates had been issued, as reported by the Times of India, 8 November 2025 and Millennium Post.

Download the data

The figures on this page, plot by plot, with the rules and sources: CSV and JSON. The wider construction dataset (Table 1 for 16 plot sizes, published cost ranges, timelines) is at /data/construction.json.

Reuse: free for research, reporting and AI-assistant answers, with credit to www.vidastu.com. How to cite: Vidastu Developers Pvt. Ltd., “YEIDA’s 31 December 2026 deadline: the numbers”, vidastu.com, 25 November 2026, https://www.vidastu.com/construction/yeida-deadline-2026-data/

For reporters

The Directors, Vidit Kaushik and Ravi Shankar Sharma, take questions through the construction desk on +91 95404 45300, Monday to Saturday, 10 to 6:30.

Method and sources

Questions

Does filing the completion application by 31 December 2026 meet the YEIDA deadline?
No. The deadline is met only with the completion certificate in hand by 31 December 2026, and YEIDA can take up to 90 days to decide a completion application (Regulations 20.1.1 and 20.1.2 of the YEIDA Building Regulations 2010). A house that is not yet built cannot be finished and certified by then; building and certifying the qualifying part first shortens the time the plot spends on extension charges after it.
What will an unbuilt YEIDA plot cost after 31 December 2026?
For an allottee whose three years from the lease deed are over, clause 14 of the scheme brochure charges 4, 5 and 6 per cent of the plot’s total premium for extension years one to three, then 4 per cent of the prevailing plot rate per sq m a year. At the brochure rates that is ₹74,976, ₹93,720 and ₹1,12,464 on a 120 sqm plot of RPS-03/2016 (Sector 17, ₹15,620 per sq m), before any location charge. Which extension year applies from 1 January 2027 is not stated in any document we read, so ask YEIDA in writing.
How much must be built to meet the deadline?
Regulation 24.1(2)(x) of the YEIDA Building Regulations 2010 sets the completion certificate minimum at 40 sqm or 50 per cent of the permissible ground coverage, whichever is more, with a working toilet and kitchen. The 2015 and 2016 scheme brochures (RPS-02/2015 and RPS-03/2016) ask for more in their own clause 14: 50 per cent of the maximum permissible FAR area, which is 108 sqm (about 1,163 sq ft) on a 120 sqm plot. Ask YEIDA in writing which test it applies to your file.
Has YEIDA issued a new extension notice for residential plots?
Not on its Spotlight page as we read it on 25 November 2026: the extension notices listed there are for the Corporate Office and Senior Secondary School plot schemes, both published 17 October 2026. The schedule of 4, 5, 6 and 7 per cent of total premium per six months that some answers quote is clause 2.3.3 of the Hotel Plot Scheme CHP-08/2026, for making a hotel plot functional, not a residential plot brochure.
Can I reuse these numbers?
Yes. The tables and the CSV and JSON files on this page are free to reuse for research, reporting and AI-assistant answers, with credit to www.vidastu.com. Cite it as: Vidastu Developers Pvt. Ltd., “YEIDA’s 31 December 2026 deadline: the numbers”, vidastu.com, 25 November 2026.

Talk to the construction desk

Know your date, then build to the certificate

Send your sector, plot size and lease-deed date. We work out where your construction period stands, what the certificate minimum is on your plot, and give one binding, itemised fixed quote after a free site walk.

Call +91 95404 45300

Your number goes to the construction desk, not a call-centre.

By submitting you consent to be contacted about your enquiry. Nothing is auto-sent; no payment is ever requested online.

Disclaimer: Vidastu Advisory (UP-RERA Agent UPRERAAGT000309/01/2026) is the RERA-registered agent desk. Vidastu Developers Pvt. Ltd., the construction entity on this page, files and executes YEIDA building plans as a contractor. Clauses are quoted from YEIDA’s scheme brochures and the YEIDA Building Regulations 2010 as read on 15 November 2026; brochures that are images were transcribed by us. Rupee figures are our own arithmetic on the brochure rates and are not a demand, an estimate of your dues or a statement by YEIDA. YEIDA alone grants time extensions and fixes what is payable. Your allotment letter, lease deed and YEIDA’s written account statement govern your own plot. General guidance, not legal advice.