16th Parkview - Gaur Yamuna City
Gautam Buddha Nagar, Uttar Pradesh: the record gives no street address
On the register16th Parkview - Gaur Yamuna City is registered with UP-RERA as UPRERAPRJ6801, registered on 31 July 2017, by Gaursons Realtech Pvt Ltd. The completion date on the register is 12 February 2025. This page is the register file as read on 10 October 2026. This desk has not investigated the project, so it gives no advice on it here; ask if you want it investigated.
- Price
- the register carries no price; the desk asks the developer for the dated sheet and sends it in writing
- Registered on
- 31 July 2017registration is registration, not approval or endorsement
- Registration type
- Ongoingunder way when it was registered
- Promoter of record
- GAURSONS REALTECH PRIVATE LIMITEDas filed; every registration under this name
- Project type
- Residential
- Declared construction period
- 117 months
- Completion date declared at registration
- 14 November 2022the date declared to UP-RERA, not a commitment to hand over a home on that date
- Completion date on the register now
- 12 February 2025see the extension entries below
- Documents on the register
- 71
- Land area, as filed
- 87756 sq m
Read from the UP-RERA register on 10 October 2026. Every line here can be checked on up-rera.in against the registration number.
Ask the desk
This page holds the register file and nothing else. Ask for anything that is not on it, or ask the desk to investigate this project; you will get an answer in writing or be told we do not have it.
Thanks, we have it.
Opening WhatsApp so we can talk now.
What this record tells a buyer
- The registration type is Ongoing: the project was already under way when it was registered, which is how projects begun before RERA registration became mandatory appear on the register.
- The promoter declared a construction period of 117 months. Across 15 residential registrations in Yamuna Expressway registered before 2023 that declare one, the median declared period is 60 months.
- The completion date declared at registration was 14 November 2022. The register now shows 12 February 2025, with 2 extension entries listed below.
- 71 documents across 20 document types are on the register for this registration. They include the sanctioned building plan, the sanctioned layout plan, the commencement certificate, the encumbrance declaration, an engineer's certificate, an architect's certificate and a chartered accountant's certificate.
- Gaursons Realtech Pvt Ltd has 11 registrations on the UP-RERA register for Gautam Buddha Nagar, made between 2017 and 2021.
- The filed address does not name a sector, so this page places the project only where the record itself does.
The full register file
2 extension entries with the register's own reasons, all 71 documents on record with download links, and the progress certificates: the complete file for 16th Parkview - Gaur Yamuna City is kept on UP-RERA Tracker by Vidastu.
Before you book 16th Parkview - Gaur Yamuna City
- Get the price in writing, dated, with its basis. Super, carpet or saleable area, and what the figure leaves out. A number on a phone call is not a price.
- Match the company on your agreement to the promoter of record, GAURSONS REALTECH PRIVATE LIMITED. Group companies often register under different names.
- Check the registration yourself on up-rera.in against UPRERAPRJ6801, including the completion date on record and the extension entries (how to read the file).
- Ask for the sanctioned building plan for your tower and compare it with the brochure.
- Pay only into the project's RERA account named in the agreement, never to a person or an agent.
- Read the draft allotment letter and agreement for sale before the first payment, not after.
- Run the EMI before the token. Our EMI calculator takes the written price, your down payment, the rate your bank quotes and the tenure; it prints nothing it is not given.
What this page does not have
- Price. No rate, basis or date is on file, so none is printed. Ask the desk for whatever is current, in writing.
- Configurations and sizes. The register does not carry unit types or sizes, and this page does not repeat a brochure.
- Amenities and payment plans. None on file.
- Distances. None on file. A distance goes on a page only from a named source with a date.
- Advice. This desk advises only on projects it has investigated. This one has not been, yet.
More from Gaursons Realtech Pvt Ltd on the register
Other registrations in Yamuna Expressway
- InvestigatedATS Allure
- InvestigatedACE Terra
- InvestigatedGaur Chrysalis (Phase 1)
- InvestigatedPurvanchal Sunbliss
- InvestigatedGaur Alaris
- InvestigatedArihant Seasons 22D
- InvestigatedVVIP Yamuna
- On the registerSpeedway Avenue
Guides for this area
Common questions
Is 16th Parkview - Gaur Yamuna City registered with UP-RERA?
Yes. 16th Parkview - Gaur Yamuna City is on the UP-RERA register as UPRERAPRJ6801, registered on 31 July 2017. Registration is registration; it is not approval or endorsement of the project.
Who is the promoter of 16th Parkview - Gaur Yamuna City?
The promoter of record is GAURSONS REALTECH PRIVATE LIMITED, as filed on the register. Check that this is the company named in your agreement before you pay.
What completion date does the register show for 16th Parkview - Gaur Yamuna City?
The register shows 12 February 2025. The date declared at registration was 14 November 2022; the change is recorded as extension entries on the register. A completion date on the register is not a commitment to hand over a home on that date.
Where is 16th Parkview - Gaur Yamuna City?
The register gives no street address for this registration beyond the district, Gautam Buddha Nagar, Uttar Pradesh.
What is the price of 16th Parkview - Gaur Yamuna City?
This page prints no price. The register carries none, and no dated rate or cost sheet from the promoter is on file with this desk. Ask the desk and you will get whatever is current in writing, or be told it is not available.
Has the completion date of 16th Parkview - Gaur Yamuna City been extended?
The register lists 2 extension entries for this registration. Each entry, with the register's own reason text, is in the full file on UP-RERA Tracker by Vidastu, linked from this page.
Read from the UP-RERA register on 10 October 2026. Directory: every registration this desk has read.