Sector 22D, Yamuna Expressway: All Projects Compared (2026)

The corridor epicenter, in one paragraph

Sector 22D on the Yamuna Expressway is the single most built-up residential pocket in the entire corridor: twelve named projects in this review, spanning every stage from a reported-sold-out registered launch to projects with no independently verifiable RERA number at all. Only three carry a fully transparent, live, directly-bookable cost sheet today: Gaur Chrysalis Phase 1 (registered, reported sold out), Eldeco Echoes of Eden (registered, under construction, Caelum tower open) and the three ACE Group filings (Terra/Edit/YXP, each separately registered). The rest, Gaur Alaris (now RERA-registered as Gaur Alaris, UPRERAPRJ950965/07/2026, though not yet independently re-confirmed by us on the portal) and Arihant Seasons 22D (reported-registered but not independently re-confirmed by us on the portal), County and Orion (no independently verifiable RERA number at all), ATS Allure (RERA now confirmed, but conflicting portal pricing and tower count), and Purvanchal Sunbliss and Greenbay The Monarque (RERA and promoter now confirmed directly on up-rera.in in follow-up reviews, but price and configuration figures still carry real, unreconciled gaps), need a direct, personal verification step before any figure below is treated as current. That verification step is the entire point of this page.

Open in Sector 22D right now

Two homes in the sector our desk can open today. Both sit on the UP-RERA register, and we will put a dated cost sheet for either one in writing.

Eldeco Echoes of Eden, Caelum tower. Registered as UPRERAPRJ125342/02/2026, with 11 January 2031 recorded on the register as the completion date. The basic sale price for Caelum is ₹11,000 per sq ft* on super area, plus other charges, as on 8 October 2026, with Haven and Elysian fully booked. Read the Echoes of Eden pages.

Eldeco Ballads of Bliss, owner resale. Registered as UPRERAPRJ921261/05/2025 and sold out since June 2025 per Eldeco's announcement, so resale is the route in. One 3 BHK of 1,550 sq.ft super area is open at ₹8,299/sq.ft* on super area plus other charges, with the full figure on the unit sheet. Read the Ballads unit.

Ask what is open in Sector 22D →
12Named projects reviewed, one sector
8/12Carry a reported RERA registration number
1Project (EOE) combining live RERA + active construction + open booking today
3Projects with a RERA or pricing gap we would not paper over

Where Sector 22D is, with a schematic map and what is built so far: Sector 22D, Yamuna Expressway explained.

Why Sector 22D, specifically

Every corridor guide on this site eventually points back here. Sector 22D sits closest to the operational stretch of the Yamuna Expressway approach to Noida International Airport, it was named in YEIDA's 2024 residual-plot land scheme, and, unlike Sectors 18 and 20 a few kilometres away, which show no named apartment supply in our review (see our four-sector buyer's guide), it is where every major Yamuna Expressway developer has chosen to build. That concentration is exactly why buyers get confused here: multiple projects with similar-sounding “peacock,” “butterfly” and lifestyle-branded names, at least one project actively marketed under two different names (Gaur Chrysalis Phase 1 vs. “Chrysalis 2.0”/Plume), and price quotes that vary by thousands of rupees per sq.ft across portals for the same address. This page exists to put every one of them in a single, sourced table, not to pick a winner for you. For a faster, at-a-glance status check across the whole corridor (this sector and beyond), see our companion live status grid, updated independently of this editorial comparison.

Which is cheapest, which is ready first, which is “best”: answered first

Cheapest quoted entry: ACE Edit, from a reported ₹85.76 lakh, but that is a smaller-format unit, not a 3 BHK-for-3 BHK comparison. Among projects with transparent per-sq.ft pricing and a live RERA filing, Eldeco Echoes of Eden's 3 BHK on the dated cost sheet (₹11,000/sq.ft* super area, plus other charges, 8 October 2026 BSP, Caelum tower) is the clearest verified entry ticket today.

Closest to possession: ACE Terra, reported for December 2028, ahead of Greenbay The Monarque (Sep 2029), Purvanchal Sunbliss (Jan 2030), Gaur Chrysalis Phase 1 (Oct 2030) and Eldeco Echoes of Eden (Jan 2031), all reported, RERA-filed target dates, not guarantees.

“Best”: we won't manufacture a single winner across twelve projects built for different buyers. Gaur Chrysalis Phase 1 is the demand proof-point (reported sold out); Eldeco Echoes of Eden is the one project combining a live RERA number, visible construction and directly bookable availability right now; Gaur Alaris is now RERA-registered as Gaur Alaris (UPRERAPRJ950965/07/2026); and County and Orion have no verifiable RERA number, while ATS Allure (RERA now confirmed, along with a 2023 delay order we dug up since) still carries a pricing/tower-count gap we're naming rather than smoothing over below.

The master matrix: one verified row per project

Project RERA status Configs Indicative price Possession Our take
Gaur Chrysalis (Ph. 1, original) UPRERAPRJ622344/11/2025, granted 4 Nov 2025, promoter Gaursons Promoters Pvt Ltd. Confirmed 3 BHK 1,910 sq.ft · 4 BHK 2,495 sq.ft (total/saleable) · 7 towers (B1 to B7), G+33/34, ~11.8 to 12 acres, 952 units, butterfly theme, ~75,000 sq.ft clubhouse Launch BSP ₹8,000/sq.ft, revised ₹11,000/sq.ft (eff. 22 Dec 2025, +37 to 38% in ~7 weeks, our calc); indicative ₹1.98 to 2.64 Cr band post-revision Reported Oct 2030 (per RERA filing) Reported Reported sold out: the sector's demand proof-point. If you want this exact building, you're shopping resale, not fresh availability.
Gaur Alaris (formerly Gaur Alaris / “Chrysalis 2.0”) RERA-registered: UPRERAPRJ950965/07/2026 (July 2026). Founder-stated 3 BHK only, 1,550 sq.ft & 1,950 sq.ft (final) · 8 towers (Phase 1), ~11.8 acres, peacock theme, ~85,000 sq.ft clubhouse + 15,000 sq.ft terrace BSP of record ₹12,000/sq.ft* super area, as on 7 September 2026, other charges extra; ₹9,000/sq.ft* super area on the closing list (3 BHK); Phase 1 fully booked on 1 September 2026 Reported 09-06-2031 (Phase 1, per RERA registration) Founder-stated Same family as Chrysalis, now separately registered under its own RERA number. Not yet independently re-confirmed by us on the portal; see our full Gaur Alaris review.
Eldeco Echoes of Eden UPRERAPRJ125342/02/2026, promoter Eldeco Sohna Projects Limited. Confirmed 3 BHK 1,550 to 1,850 sq.ft · 4 BHK/duplex 2,700 to 3,150 sq.ft · 3 towers (Haven, Elysian, Caelum), G+32, 5 acres, 558 units, VRV AC standard; 2 BHK sold out, Haven & Elysian fully booked Current BSP ₹11,000 per sq ft* super area, plus other charges, as on 8 October 2026 (Caelum only); 3 BHK on the dated cost sheet, 4 BHK/penthouse ₹2.51 to 2.93 Cr Reported Jan 2031, 30:40:30 construction-linked plan Confirmed The only project here combining live RERA, visible construction and open direct booking today: our default answer for “ready-ish and verifiable now.”
ACE Terra UPRERAPRJ683816/04/2024 Confirmed (ACE Group's site, cross-page) Per ACE's project listing; confirm current configuration and carpet area directly From ₹2.63 Cr Reported Dec 2028 Reported Earliest reported possession date on this table, worth a look if timeline matters more than entry price. Full sourced review, incl. the registered promoter entity behind the “ACE” brand here: ACE Terra: Honest Review (2026).
ACE Edit UPRERAPRJ467686/09/2025 Confirmed (ACE Group's site) Smaller-format configuration; verify against Terra/YXP before assuming a like-for-like comparison From ₹85.76 lakh Reported Not independently confirmed in this review Gap Lowest headline price on this table by a wide margin; that's a smaller product, not a cheaper version of the same apartment. Confirm size before comparing BSP.
ACE YXP UPRERAPRJ397607 Confirmed (ACE Group's site) Per ACE's project listing; confirm current configuration directly From ₹1.50 Cr Reported Not independently confirmed in this review Gap Mid-tier ACE entry between Edit and Terra: same developer group, same “verify the current launch phase” caveat.
ATS Allure UPRERAPRJ918, registered 31-07-2017, promoter ATS Realty Private Limited Confirmed (up-rera.in, direct); since independently confirmed after this row was first published 2 BHK & 3 BHK; portals disagree on tower count (2 vs. 8) and units (1,114 to 1,146), 8.48 acres consistent; RERA-filed carpet area 756 to 896 sq.ft. vs. portal super-built-up 753 to 1,350 sq.ft. Gap Sources disagree materially: cited figures ranged from ₹1.15 Cr to ₹1.53 Cr for what may be different unit types or resale vs. primary listings Not independently verified Largely possession-complete per portals; a Feb 2023 UP-RERA order found delivery still incomplete for 19 complainants as of that date and ordered possession within 60 days Confirmed (order) / Gap (current compliance) The messiest data set on this table. Don't rely on any portal figure here; pull the live RERA filing and cost sheet directly before a site visit. We since dug further, including a 2023 UP-RERA delay order: ATS Allure: Honest Review (2026).
Purvanchal Sunbliss UPRERAPRJ746863/04/2025, registered 8 Apr 2025, promoter Purvanchal Projects Private Limited Confirmed (up-rera.in, direct); since independently confirmed after this row was first published Studio to 4 BHK, 725 to 3,695 sq.ft per portals vs. a materially smaller carpet-area set (366 to 2,250 sq.ft.) per the project's own marketing site · 7 towers × 25 floors, 10.5 acres, 1,112 units Gap ~₹10,000/sq.ft Reported 29 Jan 2030 Confirmed Widest configuration spread in the sector (studio through 4 BHK) and a promoter with a genuinely checkable NCR delivery record, but its own configuration figures conflict materially across sources. We dug further, including that delivery record: Purvanchal Sunbliss: Honest Review (2026).
Greenbay The Monarque UPRERAPRJ710489/10/2025, promoter Green Bay Infrastructure Private Limited Confirmed (up-rera.in, direct); since independently confirmed after this row was first published 3.5 BHK & 4.5 BHK · ~314 reported units on 4.22 acres, part of the “Greenbay Golf Village” township Not independently confirmed in this review Gap 18 Sep 2029 Confirmed Golf-course positioning is genuinely distinctive, and the golf/township amenities do sit under a separate, older RERA filing, not this one. We dug further, including the promoter's group affiliation: Greenbay The Monarque: Honest Review (2026).
County (Yamuna Expressway) No RERA registration number surfaced in this review. Gap 3, 4 & 5 BHK per developer marketing Not published Gap Not stated; reads as pre-launch/upcoming per developer marketing Gap No independently verifiable RERA number anywhere in our source set. Treat as marketing material until a registration number is confirmed on up-rera.in.
Orion (Sector 22D) No RERA registration number surfaced in this review. Gap 3 BHK & 4 BHK, 1,800 to 3,000 sq.ft, 800 units, sited on an 11-acre parcel inside a marketed 100-acre township “On request”: no public figure Gap Not stated Gap Least transparent listing on this table: no public price and no RERA number. Get both in writing before a site visit.
Arihant Seasons 22D UPRERAPRJ974543/02/2026 Reported (portal listings; not independently confirmed by us on up-rera.in) 3 BHK & 4 BHK, 1,600 to 3,500 sq.ft · 11 to 12 towers planned, ~11.8 acres (YEIDA e-auction, Oct 2024) Pre-launch ~₹8,000/sq.ft → tentative ~₹10,000/sq.ft at launch Reported Not stated; pre-launch pricing Gap Newest land parcel in the set (Oct 2024 e-auction) and the largest tower count on paper. Still pre-launch pricing; confirm the final sanctioned plan before relying on 11 to 12 towers.

Legend: Confirmed = two or more independent sources agree, or the developer's official site states it consistently across pages; Reported = one or more named portal/media sources, not independently re-confirmed by us against the live up-rera.in filing; Gap = no verifiable figure found: named, not estimated. Every RERA number above should be independently checked at up-rera.in before any booking; portal pricing moves between phases and is never a substitute for the live cost sheet. Every registration in this table also has its own page on the UP RERA project register our desk publishes.

Why we publish gaps instead of filling them Two rows above (County and Orion) carry a genuine RERA gap: no registration number we could independently surface. A third, ATS Allure, started the same way when this page first published; a follow-up review has since confirmed its RERA number directly (UPRERAPRJ918) and turned up a 2023 UP-RERA delay order, though its price and tower-count figures still conflict across portals. We could have rounded any of these off with a plausible-sounding estimate. We didn't, because a wrong number dressed up as confident advice is worse than an honest “verify this yourself”, and because the whole reason a page like this is useful is that every other figure on it earned its “Confirmed” or “Reported” tag rather than being assumed.

How Gaur Chrysalis, Chrysalis 2.0/Plume and Eldeco EOE relate to each other

Three names on this table cause almost all of the buyer confusion in Sector 22D, so it's worth stating plainly: Gaur Chrysalis Phase 1 and Gaur Alaris (widely marketed as “Chrysalis 2.0” or “Gaur Plume”) are two separate projects by the same developer group: Chrysalis is the registered, reported-sold-out butterfly-themed original; Plume is the peacock-themed sequel, now RERA-registered as Gaur Alaris (UPRERAPRJ950965/07/2026). Neither one's registration covers the other; see our dedicated Gaur Alaris review for the full disambiguation. A third Gaurs name worth keeping separate from both: Gaurs Studio Bento is a distinct studio-apartment launch at Sector 19, Gaur Yamuna City, a different sector and a different unit type from either Chrysalis or Plume, also pre-RERA and EOI-only at this stage. See current status at Gaurs Studio Bento. Separately, Eldeco Echoes of Eden, Ballads of Bliss and Whispers of Wonder were long assumed to be one project under different campaign names, but UP-RERA records show three separate registrations by the same developer on adjacent Sector 22D plots: EOE (UPRERAPRJ125342/02/2026), Ballads of Bliss (UPRERAPRJ921261/05/2025) and Whispers of Wonder (UPRERAPRJ752382/09/2025). Verify each independently before booking. Full walkthrough in our Ballads of Bliss / WOW disambiguation.

How to verify any row yourself

For any RERA number on this page, search it directly at up-rera.in rather than trusting a portal listing or a broker's claim; that includes the nine rows we've tagged “Confirmed” or “Reported” above, since portal data can lag or misstate a live filing. For current pricing on any project, ask for the RERA-filed cost sheet, not a WhatsApp-forwarded price list. And for County and Orion, treat the absence of a verifiable RERA number as the finding itself, not as an invitation to fill it in with a guess; ATS Allure's number is now confirmed (see our full review), but its other figures still need the same caution.

Sources cited above
  1. Vidastu, YEIDA Sector-by-Sector Buyer's Guide: 22D, 22A, 18, 20 (companion review; primary sourcing for Chrysalis, Plume, EOE and the ACE trio)
  2. Gaur Chrysalis: official Price List and Brochure
  3. Business Standard: Gaurs Group Yamuna Expressway project coverage (8 Nov 2025)
  4. Gaur Alaris (“Gaur Alaris”): our channel-partner project site
  5. Eldeco Echoes of Eden: our channel-partner project site
  6. ACE Group: official Yamuna Expressway projects page (Terra, Edit, YXP)
  7. SquareYards: ATS Allure, Sector 22D Yamuna Expressway
  8. UP RERA: ATS Allure project summary, registration UPRERAPRJ918 (confirmed directly)
  9. Vidastu, ACE Terra, Yamuna Expressway: Honest Review (2026)
  10. Vidastu, ATS Allure, Yamuna Expressway: Honest Review (2026)
  11. SquareYards: Purvanchal Sunbliss, Sector 22D Yamuna Expressway
  12. 99acres: Greenbay The Monarque, Sector 22D Yamuna Expressway
  13. County Yamuna Expressway: developer marketing site
  14. Orion Sector 22D Yamuna Expressway: developer marketing site
  15. 360PropGuide: Arihant Group's upcoming project in Sector 22D
  16. UP RERA: official project registration search
Vidit Kaushik, Director, Vidastu Developers Pvt. Ltd.

Vidit Kaushik

Civil Engineering, BITS Pilani · UP-RERA Agent UPRERAAGT000309/01/2026 · Director, Vidastu Developers Pvt. Ltd.

By Vidit Kaushik Published 9 Jul 2026 UP-RERA Agent UPRERAAGT000309/01/2026 ~10 min read

Talk to the desk

Weighing two or three of these against each other?

Tell our advisory desk which rows you're shortlisting; we'll pull the live RERA filing and current cost sheet for each before you visit any sales gallery.

+91 98114 05300

Mon to Sat, 10 to 7 · Sunday, phone & WhatsApp only

Your number goes to the desk, not a call-centre.

By submitting you consent to be contacted about your enquiry. Nothing is auto-sent; no payment is ever requested online.

Frequently asked questions

Which Sector 22D project is cheapest right now?
By reported starting price, ACE Edit (from ₹85.76 lakh) is the lowest publicly quoted entry ticket in our source set, but that reflects a smaller configuration, not a like-for-like comparison with 3 BHK projects. Among projects with transparent per-sq.ft pricing and an active RERA filing, Eldeco Echoes of Eden's 3 BHK on the dated cost sheet (₹11,000/sq.ft* super area, plus other charges, 8 October 2026 BSP) is the clearest verified entry point today.
Which Sector 22D project is closest to possession?
ACE Terra carries the earliest declared completion date in our set, December 2028, followed by Greenbay The Monarque (September 2029), Purvanchal Sunbliss (January 2030), Gaur Chrysalis Phase 1 (October 2030) and Eldeco Echoes of Eden (January 2031). These are reported, RERA-filed target dates, not guarantees; always check the live RERA extension history before treating any date as final.
Which Sector 22D project is best?
There is no single best project; it depends on what you're optimising for. Gaur Chrysalis Phase 1 proved out demand (reported sold out); Eldeco Echoes of Eden is the only project on this list combining a live RERA filing, active construction and directly bookable availability today; Gaur Alaris is now RERA-registered as Gaur Alaris (UPRERAPRJ950965/07/2026); County and Orion have no verifiable RERA number at all, and ATS Allure (RERA now confirmed, but its price and tower-count figures still conflict across portals) has the gaps we would not paper over. Match the project to your own risk tolerance, not to a superlative.
Is Gaur Chrysalis the same project as Gaur Plume or Gaur Alaris?
No. Gaur Chrysalis Phase 1 (RERA UPRERAPRJ622344/11/2025) is a separate, already-registered, reported-sold-out project, the butterfly-themed original. Gaur Alaris, widely marketed as Gaur Chrysalis 2.0 or Gaur Plume, is a distinct later phase with its own peacock theme, now RERA-registered as Gaur Alaris (UPRERAPRJ950965/07/2026). Never accept Chrysalis Phase 1's RERA number as cover for a Gaur Alaris booking.
How many Sector 22D projects actually have a confirmed RERA number?
In this review: Gaur Chrysalis Phase 1, Eldeco Echoes of Eden, ACE Terra, ACE Edit, ACE YXP, ATS Allure, Purvanchal Sunbliss, Greenbay The Monarque and Arihant Seasons 22D all carry a confirmed or reported RERA registration number: nine of the twelve rows in our table (ATS Allure's UPRERAPRJ918, Purvanchal Sunbliss's UPRERAPRJ746863/04/2025 and Greenbay The Monarque's UPRERAPRJ710489/10/2025 were all confirmed directly on up-rera.in in follow-up reviews, though ATS Allure's price and tower-count figures still conflict across portals). Gaur Alaris is now RERA-registered as Gaur Alaris (UPRERAPRJ950965/07/2026). County and Orion surfaced no independently verifiable RERA number in this review. Verify every number directly at up-rera.in before paying anything.
Are there resale flats available in Sector 22D?
It varies project to project, and we don't track secondary-market listings live across the sector. The one project where resale is most likely to be your only route in is Gaur Chrysalis Phase 1, which is reported sold out on the primary market; anyone buying that exact building today is almost certainly buying resale. For the other named projects here, most are still under construction with primary availability open, so resale is either not yet a factor or not something we've independently confirmed; ask our desk to check current secondary-market availability for a specific project before assuming any exists.

Disclosure: This is independent research by Vidastu Developers Pvt. Ltd. / Vidastu Advisory (sister brand, UP-RERA-registered agent UPRERAAGT000309/01/2026), an authorised channel partner, not the developer of any project named above. Figures are dated and sourced inline; “Reported” means one or more named sources, not independent confirmation by us against the live RERA filing; “Gap” means no verifiable figure was found, not that nothing exists; “Confirmed” means two or more independent sources agree, or the developer's official site states it consistently. This page states no assured returns and does not solicit bookings for any project; verify every RERA registration directly at up-rera.in and every price against the live, RERA-filed cost sheet before paying anything.