The short answer
I just won a YEIDA plot. What do I do next? Seven stages take a fresh allotment to a certified, move-in home: (1) verify your allotment letter, (2) pay the premium and take possession when YEIDA offers it, (3) get the lease deed registered and the plot mutated, (4) design the house with Vaastu built in, (5) get BPMS map (naksha) approval, (6) build under a written milestone contract, (7) obtain the completion certificate and move in. The whole journey must end with a completion certificate, within three years of the lease deed (clause 14 of the scheme brochure). For RPS-10/2026 and the 2024 schemes the brochure puts possession at approximately five years after allotment (clause 13(iv)), so the first stages are payment and paperwork; the 31 December 2026 date is for earlier allottees whose lease deeds are already executed.
Your 7 stages, allotment to keys
This page is the map. Each stage links to the deeper guide where one exists; start here, then go as deep as you need.
Verify your allotment letter. Before you pay anyone or sign a transfer, confirm the allotment letter is genuine against YEIDA records, the single most common place fresh allottees get cheated. How to verify a YEIDA allotment letter.
Pay the premium & take possession. Pay YEIDA’s dues on the PIMS portal: for RPS-10/2026, 100 per cent of the premium within 60 days of the allotment letter (clause 8). Possession comes when YEIDA offers it, which the brochure puts at approximately five years after allotment (clause 13(iv)); the lease deed is then executed within 180 days (clause 22(ii)). A building-plan sanction cannot proceed with dues pending. The lease deed starts your three-year construction period (clause 14 of the scheme brochure); the 31 December 2026 date is for earlier allottees whose lease deeds were already executed.
Execute the lease deed, registry & mutation. Get the lease deed executed with YEIDA, registered at the sub-registrar (IGRS-UP) and the plot mutated to your name; registered title is what lenders, the completion certificate and any future resale depend on. Lease deed & registry, step by step.
Design with Vaastu built in. A Council of Architecture-registered architect plans floors (G+1/G+2), rooms, parking and basement within your plot’s sanctioned FAR, ground coverage and height, with Vaastu integrated at the drawing stage, not retrofitted. Vaastu for your YEIDA plot.
Get BPMS map (naksha) approval. File the building plan online via the YEIDA BPMS portal, the only legal route since 1 August 2024. Smart-DCR checks the drawings against the byelaws before the fee is paid. YEIDA building-plan approval, step by step.
Build under a written milestone contract. Lock scope, named material spec, dated milestones, payment stages and defect-liability terms before any work; payments release against completed stages, never a large advance. Turnkey vs labour vs item-rate · what drives the cost.
Get the completion certificate & move in. Apply for the YEIDA completion/occupancy certificate (required for utilities, a home loan, registry and resale), then handover. The full build runs on dated milestones. The full build sequence.
Find your sector
Recently allotted in an RPS scheme? Your plot sits in one of these sectors; each has a construction guide with permissible floors, build timeline and the deadline math.
| Scheme | Sector(s) | Plot sizes | Notes |
|---|---|---|---|
| RPS-10/2026 | 18, 24A, 15C | ~120 to 290 sqm | ~973 plots; drawn 18 Jun 2026, newest allottees |
| RPS-09/2025 | 18 (Pocket-9B) | 200 sqm | 276 plots |
| RPS-08(A)/2024 | 24A | ~120 to 260 sqm | 451 plots, near Jewar / Noida International Airport |
| RPS-08/2024 | 18, 20, 22D, 16 | varies | drawn Oct 2024 |
Know your plot size? Each plot-size guide works out the Table 1 ground coverage, FAR, setbacks and completion-certificate minimum for that size, with a cost build-up against dated published ranges: 60 · 90 · 120 · 162 · 183 · 184 · 200 · 223 · 250 · 260 · 290 · 300 · 500 · 1,000 · 2,000 · 4,000 sqm.
What will it cost to build?
There is no honest per-square-foot figure sight-unseen. Your number moves with plot size (and how much built-up area you put on it), number of floors (G+1 vs G+2 vs basement), finish level, and site/soil conditions. Vidastu doesn’t quote a rate card; you get one binding, itemised fixed quote after a free site walk, every inclusion and exclusion named. See what drives the cost, then send your sector and plot size for a quote.